III. Characteristics of thermal energy and coolant to be measured for the purpose of commercial accounting and quality control of heat supply. The Ministry of Construction proposes new rules for commercial metering of heat and coolant New rules for commercial metering of heat

115. If there are no metering devices at the metering points or the operation of metering devices for more than 15 days of the billing period, the determination of the amount of thermal energy spent on heating and ventilation is carried out by calculation and is based on the recalculation of the base indicator for the change in outside air temperature for the entire billing period.

116. The value of the heat load specified in the heat supply contract is taken as the base indicator.

117. The base indicator is recalculated based on the actual average daily outside air temperature for the calculation period, taken according to meteorological observations of the weather station of the territorial executive body closest to the heat consumption facility, which carries out the functions of providing public services in the field of hydrometeorology.

If, during the period of cutting the temperature graph in the heating network at positive outside temperatures, there is no automatic control of the heat supply for heating, and also if the cutting of the temperature graph is carried out during a period of low outdoor temperatures, the value of the outside air temperature is taken equal to the temperature indicated at the beginning of the cut graphics. When automatically regulating the heat supply, the actual temperature value indicated at the beginning of the graph cutting is taken.

118. In the event of a malfunction of metering devices, the expiration of their verification period, including removal from work for repair or verification for up to 15 days, the average daily amount of thermal energy and coolant determined from the metering devices over time is taken as the base indicator for calculating thermal energy and coolant normal operation during the reporting period, reduced to the calculated outside air temperature.

119. If the deadlines for submitting instrument readings are violated, the amount of thermal energy and coolant determined by metering devices for the previous billing period, reduced to the calculated outside air temperature, is taken as the average daily indicator.

If the previous billing period falls on a different heating period or there is no data for the previous period, the amount of thermal energy and coolant is recalculated in accordance with paragraph 121 of these Rules.

120. The amount of thermal energy and coolant spent on hot water supply, in the presence of separate metering and temporary malfunction of devices (up to 30 days), is calculated based on the actual consumption determined by metering devices for the previous period.

121. In the absence of separate metering or inoperative condition of the devices for more than 30 days, the amount of thermal energy and coolant spent on hot water supply is assumed to be equal to the values ​​​​established in the heat supply contract (the amount of heat load on hot water supply).

122. When determining the amount of thermal energy and coolant, the amount of thermal energy supplied (received) in the event of emergency situations is taken into account. Emergency situations include:

a) operation of the heat meter at coolant flow rates below the minimum or above the maximum limit of the flow meter;

b) operation of the heat meter when the coolant temperature difference is below the minimum value established for the corresponding heat meter;

125. The amount of coolant (thermal energy) lost due to a leak is calculated in the following cases:

a) a leak, including a leak on consumer networks up to the metering station, has been identified and documented in joint documents (bilateral acts);

b) the amount of leakage recorded by the water meter when feeding independent systems exceeds the standard.

126. In the cases specified in paragraph 125 of these Rules, the leakage value is determined as the difference in the absolute values ​​of the measured values ​​without taking into account errors.

In other cases, the amount of coolant leakage determined in the heat supply contract is taken into account.

127. The mass of the coolant consumed by all consumers of thermal energy and lost in the form of leakage in the entire heat supply system from the thermal energy source is defined as the mass of the coolant consumed by the thermal energy source to recharge all pipelines of water heating networks, minus intra-station expenses for own needs during production electrical energy and in the production of thermal energy, for the production and economic needs of the objects of this source and intra-station technological losses by pipelines, units and devices within the boundaries of the source.

V. The procedure for distributing losses of thermal energy and coolant between heating networks in the absence of metering devices at the boundaries of adjacent heating networks

128. The distribution of losses of thermal energy, coolant, as well as the amount of thermal energy, coolant transferred between heating networks of heat supply organizations and heating network organizations in the absence of metering devices at the boundaries of adjacent parts of heating networks, is carried out by calculation as follows:

a) in relation to thermal energy transferred (received) at the border of the balance sheet of adjacent heating networks, the calculation is based on the balance of the amount of thermal energy supplied to the heating network and consumed by heat consuming installations of consumers (for all owner organizations and (or) other legal owners of adjacent heating networks) for all sections of pipelines at the border(s) of the balance sheet of adjacent sections of the heating network, taking into account heat energy losses associated with emergency leaks and technological losses (pressure testing, testing), losses through damaged thermal insulation in adjacent heating networks, which are documented in acts , standards for technological losses during the transfer of thermal energy and losses exceeding the approved values ​​(excessive losses);

b) in relation to the coolant transferred at the border of the balance sheet of adjacent heating networks, the calculation is based on the balance of the amount of coolant supplied to the heating network and consumed by heat-consuming installations of consumers, taking into account coolant losses associated with emergency coolant leaks, documented in acts, standards for technological losses during transfer of thermal energy approved in accordance with the established procedure, and losses exceeding the approved values ​​(exceeding norms).

129. The distribution of excess losses of thermal energy and coolant between adjacent heating networks is carried out in quantities proportional to the values ​​of the approved standards for technological losses and losses of thermal energy, taking into account emergency leaks of coolant through damaged thermal insulation.

130. In the case of transfer of thermal energy, coolant through a section of the heating network owned by the consumer, when distributing losses of thermal energy, coolant and excess losses of thermal energy, coolant, the specified heating networks are considered as adjacent heating networks.

In accordance with the Federal Law "On Heat Supply", the Government of the Russian Federation decides:

1. Approve the attached Rules for commercial metering of thermal energy and coolant.

2. Federal executive authorities must bring their regulatory legal acts into compliance with this resolution within 3 months.

3. The Ministry of Construction and Housing and Communal Services of the Russian Federation must approve within 2 weeks the methodology for commercial accounting of thermal energy and coolant.

Chairman of the Government
Russian Federation
D. Medvedev

Rules for commercial metering of thermal energy and coolant

I. General provisions

1. These Rules establish the procedure for organizing commercial metering of thermal energy and coolant, including:

A) requirements for metering devices;
b) characteristics of thermal energy, coolant, subject to measurement for the purpose of commercial accounting of thermal energy, coolant and quality control of heat supply;
c) the procedure for determining the amount of supplied thermal energy and coolant for the purpose of commercial accounting of thermal energy and coolant (including by calculation);
d) the procedure for distributing losses of thermal energy and coolant by heating networks in the absence of metering devices at the boundaries of adjacent heating networks.

2. The methodology for commercial accounting of thermal energy and coolant is determined by the methodology approved by the Ministry of Construction and Housing and Communal Services of the Russian Federation (hereinafter referred to as the methodology).

3. The terms used in these Rules mean the following:

“commissioning of a metering unit” - a procedure for checking the compliance of a thermal energy metering unit with the requirements of regulatory legal acts and design documentation, including drawing up a commissioning report for a thermal energy metering unit;

“water meter” is a measuring device designed to measure the volume (mass) of water (liquid) flowing in a pipeline through a section perpendicular to the direction of flow velocity;

“operating time of metering devices” - the time interval during which, based on the readings of metering devices, thermal energy is taken into account, as well as the mass (volume) and temperature of the coolant are measured and recorded;

“heating network output” - the output of heating networks from a source of thermal energy in a certain direction;

“computer” is a component of a heat meter that receives signals from sensors and provides calculation and accumulation of data on the amount of thermal energy and coolant parameters;

“dependent connection diagram for a heat-consuming installation” - a diagram for connecting a heat-consuming installation to a heating network, in which the coolant from the heating network flows directly into the heat-consuming installation;

“closed water heat supply system” - a complex of technologically interconnected engineering structures designed for heat supply without extracting hot water (coolant) from the heating network;

“measuring metering system” - a multi-channel measuring instrument, including channels for measuring thermal energy with measuring components - heat meters, as well as additional measuring channels for the mass (volume) of the coolant and its parameters - temperature and pressure;

“individual heating point” - a set of devices for connecting a heat-consuming installation to a heating network, converting the parameters of the coolant and distributing it by type of heat load for one building, structure or structure;

“quality of thermal energy” - a set of parameters (temperatures and pressures) of the coolant used in the processes of production, transmission and consumption of thermal energy, ensuring the suitability of the coolant for the operation of heat-consuming installations in accordance with their purpose;

“saturated steam” - water vapor that is in thermodynamic equilibrium with the water in contact with it;

“independent connection diagram for a heat-consuming installation” - a diagram for connecting a heat-consuming installation to a heating network, in which the coolant coming from the heating network passes through a heat exchanger installed at a heating point, where it heats the secondary coolant, which is subsequently used in the heat-consuming installation;

“failure of measuring instruments of a metering unit” - a state of measuring instruments in which the metering unit does not comply with the requirements of regulatory legal acts, regulatory and technical and (or) design (project) documentation (including due to the expiration of the verification period for measuring instruments included in composition of the metering unit, violation of installed seals, as well as work in emergency situations);

“open water heat supply system” - a complex of technologically interconnected engineering structures designed for heat supply and (or) hot water supply by extracting hot water (coolant) from the heating network or extracting hot water from hot water supply networks;

“superheated steam” - water vapor having a temperature higher than the saturation temperature at a certain pressure;

“make-up” is a coolant additionally supplied to the heat supply system to replenish its technological consumption and losses during the transfer of thermal energy;

“metering device” - a measuring instrument that includes technical devices that perform the functions of measuring, accumulating, storing and displaying information about the amount of thermal energy, as well as mass (volume), temperature, coolant pressure and operating time of the devices;

“coolant flow” - mass (volume) of coolant passing through the cross-section of the pipeline per unit of time;

"flow meter" - a device designed to measure coolant flow;

“calculation method” - a set of organizational procedures and mathematical actions to determine the amount of thermal energy and coolant in the absence of metering devices or their inoperability, used in the cases established by these Rules;

“temperature graph cutting” - maintaining a constant temperature of the coolant in the heating network, regardless of the outside air temperature;

“heat meter” is a device designed to measure the thermal energy emitted by the coolant or consumed together with it, which is a single structure or consisting of component elements - flow converters, flow meters, water meters, temperature (pressure) sensors and a computer;

“technical operation of a metering unit” - a set of operations for maintenance and repair of elements of a thermal energy metering unit, ensuring the reliability of measurement results;

“metering unit” - a technical system consisting of measuring instruments and devices that provide accounting for thermal energy, mass (volume) of the coolant, as well as monitoring and recording the parameters of the coolant;

“coolant leakage” - loss of water (steam) through leaks in process equipment, pipelines and heat-consuming installations;

“Measuring accounting system form” - a document drawn up in relation to the measuring system of the accounting unit and reflecting, among other things, the composition of the accounting unit and changes in its composition;

“functional failure” - a malfunction in the system of the metering unit or its elements, in which the metering of thermal energy, mass (volume) of the coolant stops or becomes unreliable;

“central heating point” is a set of devices for connecting heat-consuming installations of several buildings, structures or structures to the heating network, as well as for converting the parameters of the coolant and distributing it according to the types of heat load.

4. Commercial accounting of thermal energy and coolant is organized for the purposes of:

A) carrying out settlements between heat supply, heating network organizations and consumers of thermal energy;
b) control over the thermal and hydraulic operating conditions of heat supply systems and heat-consuming installations;
c) control over the rational use of thermal energy and coolant;
d) documenting coolant parameters - mass (volume), temperature and pressure.

5. Commercial metering of thermal energy and coolant is carried out using metering devices that are installed at the metering point located on the border of the balance sheet, if a heat supply agreement, a contract for the supply of thermal energy (power), coolant or a contract for the provision of services for the transfer of thermal energy and coolant ( hereinafter referred to as the agreement) no other accounting point has been determined.

6. Metering units put into operation before the entry into force of these Rules can be used for commercial metering of thermal energy and coolant until the expiration of the service life of the main metering devices (flow meter, heat calculator) included in the metering units.

7. After 3 years from the date of entry into force of these Rules, heat meters that do not meet the requirements of these Rules cannot be used for installation in both new and existing metering units.

8. Heat supply organizations or other persons do not have the right to require the consumer of thermal energy to install devices or additional devices at the metering station that are not provided for by these Rules.

9. The heat supply organization, heating network organization and consumer have the right to install additional devices at the metering station to control the supply and consumption of thermal energy, coolant, including for remote readings from the heat meter, without interfering with the commercial metering of heat energy, coolant and other affecting the accuracy and quality of measurements.

10. If remote reading equipment is installed at the metering station, the heat supply (heating network) organization and the consumer have the right to gain access to the specified system in the manner and on the terms determined by the contract.

11. If a single thermal energy consumer is connected to the heating network emanating from a source of thermal energy and this heating network belongs to the specified thermal energy consumer by right of ownership or other legal basis, by agreement of the parties to the contract it is allowed to keep records of the consumed thermal energy according to the readings of the device metering installed at the metering unit for the thermal energy source.

12. If one of the parties to the contract, obligated in accordance with federal laws to install a metering device, does not fulfill this obligation, the other party to the contract is obliged, in the manner established by the legislation of the Russian Federation, to install a metering device to make payments under the contract.

13. If both parties to the contract have installed a metering device, for commercial metering of thermal energy and coolant under the contract, the readings of the metering device that is installed at the balance sheet boundary are used.

If there are 2 equivalent metering units on opposite sides of the balance sheet boundary, for commercial metering of thermal energy and coolant, the readings of the metering unit are taken, providing metering with a minimum error. The error in this case consists of the amount of unmeasured heat losses from the balance sheet boundary to the metering unit and the reduced measurement error.

14. The metering devices used must comply with the requirements of the legislation of the Russian Federation on ensuring the uniformity of measurements in force at the time the metering devices are put into operation.

After the interval between verifications has expired or after the metering devices fail or are lost, if this happened before the expiration of the inter-verification interval, metering devices that do not comply with the requirements of the legislation of the Russian Federation on ensuring the uniformity of measurements are subject to verification or replacement with new metering devices.

15. Commercial metering of thermal energy and coolant is organized at all delivery and reception points.

16. Commercial accounting of thermal energy and coolant supplied to consumers of thermal energy and coolant can be organized by both heat supply organizations, heating network organizations, and consumers of thermal energy.

17. Organization of commercial accounting of thermal energy and coolant, unless otherwise provided by the provisions of these Rules, includes:

A) obtaining technical specifications for the design of a metering unit;
b) design and installation of metering devices;
c) commissioning of a metering unit;
d) operation of metering devices, including the procedure for regularly taking meter readings and using them for commercial metering of thermal energy and coolant;
e) verification, repair and replacement of metering devices.

18. Issuance of technical specifications for the installation of a metering unit (device), commissioning, sealing of metering units (devices) and participation in commissions for the acceptance of metering units (devices) is carried out without charging a fee to the thermal energy consumer.

19. Metering units are installed in a place as close as possible to the boundary of the pipelines’ balance sheet, taking into account the real possibilities at the facility.

20. At thermal energy sources, metering units are installed at each outlet of the heating network.

21. The selection of thermal energy and coolant for the own and economic needs of the thermal energy source is organized up to the metering units at the terminals. In other cases, the selection of thermal energy and coolant must be carried out through separate metering units.

The selection of coolant for replenishment of heat supply systems with the installation of a separate meter is carried out from the return pipeline after the flow sensor along the flow of the coolant. Pressure sensors can be installed both before and after the flow sensor. Temperature sensors are installed after the flow sensor along the coolant flow.

22. If sections of the heating network belong on the right of ownership or other legal basis to different persons, or if there are jumpers between heating networks that belong on the right of ownership or other legal basis to different persons, metering units must be installed at the border of the balance sheet.

23. Collection of information about the readings of metering devices, the amount of supplied (received, transported) thermal energy, coolant, the amount of thermal energy in the supplied (received, transported) hot water, the number and duration of violations that occur in the operation of metering devices, and other information provided for in the technical documentation, displayed by metering devices, as well as taking readings from metering devices (including using telemetric systems - remote reading systems) are carried out by the consumer or the heating network organization, unless otherwise provided by the agreement with the heat supply organization.

24. The consumer or heating network organization provides the organization providing water supply and (or) sanitation, before the end of the 2nd day of the month following the billing month, information on the readings of metering devices as of the 1st day of the month following the billing month, if other deadlines are not established by the legislation of the Russian Federation, as well as information about current readings of metering devices within 2 business days after receiving a request for such information from the heat supply organization. Such information is sent to the heat supply organization in any available way (postal mail, fax, telephone message, electronic message using the Internet), allowing confirmation of receipt of the specified information by the heat supply organization.

If the technical characteristics of the metering devices and metering units used allow the use of telemetric systems for transmitting meter readings and there is financial and technical support for the installation of telemetric modules and telemetric software, the presentation (taking) of meter readings is carried out remotely using such telemetric systems.

25. The consumer or heating network organization is obliged to ensure unimpeded access for representatives of the heat supply organization or, at the direction of the heat supply organization, representatives of another organization to metering units and metering devices to verify the readings of metering devices and check compliance with the operating conditions of the metering unit devices.

26. If, during the reconciliation process, a discrepancy is found in the information about the readings of the metering devices of the consumer or heating network organization regarding the volume of supplied (received) heat energy, coolant with the information provided by the consumer or heating network organization, the heat supply organization draws up a reconciliation report of the readings of the metering devices, signed by representatives consumer or heating network organization and heat supply organization.

If the representative of the consumer or heating network organization does not agree with the contents of the act of reconciling meter readings, the representative of the consumer or heating network organization marks the act as “acquainted” and affixes a signature. Objections of the consumer or heating network organization are indicated in the act or sent to the heat supply organization in writing in any way that allows confirmation of receipt of the document by the consumer or heating network organization. If a representative of a consumer or heating network organization refuses to sign the act of reconciling meter readings, such act is signed by a representative of the heat supply organization with the note “the representative of the consumer or heating network organization refused to sign.”

The act of reconciling meter readings is the basis for recalculating the volume of supplied (received) heat energy and coolant from the day of signing the act of reconciling meter readings until the day of signing the next act.

27. In order to control the volumes of supplied (received) heat energy and coolant, the heat supply organization or consumer or heating network organization has the right to use control (parallel) metering devices, provided that one of the parties to the contract notifies the other party to the contract about the use of such metering devices.

Control (parallel) metering devices are installed on the networks of the heat supply organization, heating network organization or consumer in places that allow commercial metering of heat energy, coolant supplied to the consumer, heating network organization.

If the readings of the control (parallel) metering devices and the main metering devices differ by more than the measurement error of such metering devices for a period of at least one billing month, the person who installed the control (parallel) metering device may require the other party to carry out extraordinary accounting verification of the metering device operated by this party.

28. The readings of the control (parallel) metering device are used for the purpose of commercial metering of thermal energy, coolant for the period of malfunction, verification of the main metering device, as well as in case of violation of the deadlines for submitting metering readings.

29. Installation, replacement, operation and verification of control (parallel) metering devices are carried out in accordance with the procedures provided for installation, replacement, operation and verification of main metering devices.

30. The person who installed the control (parallel) metering device is obliged to provide the other party to the contract (consumer, heating network organization, heat supply organization) with unhindered access to the control (parallel) metering devices in order to monitor the correct installation and operation of the control (parallel) metering device.

31. Commercial accounting of thermal energy and coolant by calculation is allowed in the following cases:

A) absence of metering devices at metering points;
b) malfunction of the meter;
c) violation of the deadlines established by the contract for submitting readings from metering devices that are the property of the consumer.

32. In case of non-contractual consumption of thermal energy and coolant, the amount of thermal energy and coolant used by the consumer is determined by calculation.

II. Requirements for metering devices

33. The metering unit is equipped with heat meters and metering devices, the types of which are included in the Federal Information Fund for Ensuring the Uniformity of Measurements.

34. A heat meter consists of flow and temperature (pressure) sensors, a calculator or a combination thereof. When measuring superheated steam, a steam pressure sensor is additionally installed.

Heat meters are equipped with standard industrial protocols and can be equipped with interfaces that allow remote data collection in an automatic (automated) mode. These connections should not affect the metrological characteristics of the heat meter.

If the data determined remotely and the data read directly from the heat meter do not match, the basis for determining the payment amount is the data read directly from the heat meter.

35. The design of heat meters and metering devices included in the heat meters ensures limited access to their parts in order to prevent unauthorized settings and interference, which can lead to distortion of measurement results.

36. In heat meters, correction of the internal clock of the calculator is allowed without opening the seals.

37. The heat meter calculator must have an indelible archive in which the main technical characteristics and adjustment coefficients of the device are recorded. Archive data is displayed on the device display and (or) computer. The adjustment coefficients are entered into the device passport. Any changes must be recorded in the archive.

Design of metering units

38. For a thermal energy source, the design of a metering unit measuring system is developed on the basis of a technical specification prepared by the owner of the thermal energy source and agreed with the adjacent heat supply (heating network) organization in terms of compliance with the requirements of these Rules, the terms of the contract and the conditions for connecting the thermal energy source to the heat supply system.

39. The design of a metering unit for objects other than thermal energy sources is developed on the basis of:

A) technical conditions issued by the heat supply organization at the request of the consumer;
b) the requirements of these Rules;
c) technical documentation for metering devices and measuring instruments.

40. Specifications contain:

A) name and location of the consumer;
b) data on thermal loads for each type;
c) calculated parameters of the coolant at the point of delivery;
d) temperature graph of coolant supply depending on the outside air temperature;
e) requirements for ensuring the ability to connect the metering unit to the system for remote reading of the metering device using standard industrial protocols and interfaces, with the exception of requirements for installing communication means if the heat supply organization uses or plans to use such means;
f) recommendations regarding measuring instruments installed at the metering station (the heat supply organization does not have the right to impose specific types of metering devices on the consumer, but for the purpose of unification and the possibility of organizing remote collection of information from the metering station, it has the right to make recommendations).

41. The heat supply organization is obliged to issue technical specifications for the installation of a metering device within 15 working days from the date of receipt of the consumer’s request.

42. If within the specified period the heat supply organization does not issue technical specifications or issues technical specifications that do not contain the information established by these Rules, the consumer has the right to independently develop a design for a metering unit and install the metering device in accordance with these Rules, of which he is obliged to notify heating supply organization.

43. If there is a ventilation and process heat load, the technical conditions are accompanied by an operating schedule and calculation of the power of heat-consuming installations.

44. The metering unit project contains:

A) a copy of the heat supply agreement with attached statements of delineation of balance sheet ownership and information on design loads for existing facilities. For newly commissioned facilities, information about design loads or connection conditions is attached;
b) plan for connecting the consumer to the heating network;
c) schematic diagram of a heating point with a metering unit;
d) plan of the heating point indicating the installation locations of sensors, placement of metering devices and cable wiring diagrams;
e) electrical and wiring diagrams for connecting metering devices;
f) a configuration database entered into the heat meter (including when switching to summer and winter operating modes);
g) a scheme for sealing measuring instruments and devices included in the metering unit, in accordance with paragraph 71 of these Rules;
h) formulas for calculating thermal energy and coolant;
i) coolant flow rate for heat-consuming installations by hour of the day in winter and summer;
j) for metering units in buildings (optional) - a table of daily and monthly heat energy consumption for heat-consuming installations;
k) forms of reporting sheets of meter readings;
l) wiring diagrams for installing flow meters, temperature sensors and pressure sensors;
m) specification of the equipment and materials used.

45. The diameter of the flow meters is selected in accordance with the calculated thermal loads so that the minimum and maximum coolant flow rates do not go beyond the normalized range of the flow meters.

46. ​​Drain devices (drainers) are provided:

A) on the supply pipeline - after the primary coolant flow converter;
b) on the return (circulation) pipeline - to the primary coolant flow converter.

48. The equipment set includes mounting inserts for replacing primary coolant flow converters and flow meters.

49. The design of a metering unit installed at a thermal energy consumer is subject to agreement with the heat supply (heating network) organization that issued the technical specifications for the installation of metering devices.

50. The consumer sends a copy of the metering unit design to the heat supply (heating network) organization for approval. If the metering unit project does not comply with the provisions of paragraph 44 of these Rules, the heat supply (heating network) organization is obliged, within 5 working days from the date of receipt of a copy of the metering unit project, to send a notification to the consumer about the provision of the missing documents (information).

In this case, the deadline for receipt of the metering unit project for approval is determined from the date of submission of the revised project.

51. The heat supply (heating network) organization does not have the right to refuse to approve the metering unit project if it complies with paragraph 44 of these Rules. In case of failure to provide information on approval or comments on the metering unit project within 15 working days from the date of receipt of a copy of the metering unit project, the project is considered approved.

Commissioning of a metering unit installed at a thermal energy source

52. Installed metering units (measuring systems of metering units), which have undergone trial operation, are subject to commissioning.

53. To commission the metering unit installed at the thermal energy source, the owner of the thermal energy source appoints a commission for commissioning the metering unit (hereinafter referred to as the commission) consisting of the following:

A) representative of the owner of the thermal energy source;
b) a representative of an adjacent heating network organization;
c) a representative of the organization carrying out installation and commissioning of the equipment being commissioned.

54. The representatives specified in paragraph 53 of these Rules are called by the owner of the thermal energy source no later than 10 working days before the day of expected acceptance by sending written notifications to the members of the commission.

55. To put the metering unit into operation, the owner of the thermal energy source submits to the commission:

A) schematic diagrams for connecting the terminals of the thermal energy source;
b) acts of delimitation of balance sheet ownership;
c) projects of metering units agreed upon by the heat supply (heating network) organization in the manner established by these Rules;
d) factory passports of the components of the metering unit, containing technical and metrological characteristics;
e) certificates of verification of instruments and sensors subject to verification, with valid verification marks;
f) form of the measuring system of the metering unit (if such a system is available);
g) the installed system, including instruments that record coolant parameters;
h) a statement of continuous operation of devices for 3 days.

56. When putting the metering unit into operation, the following is checked:

A) compliance of the serial numbers of measuring instruments with the numbers indicated in their passports;
b) compliance of the measurement ranges of parameters allowed by the temperature schedule and the hydraulic operating mode of heating networks with the values ​​of the specified parameters determined by the contract and the conditions of connection to the heat supply system;
c) the quality of installation of measuring instruments and communication lines, as well as compliance of installation with the requirements of technical and design documentation;
d) the presence of seals from the manufacturer or repair company and the verifier.

57. When commissioning the measuring system of a metering unit at a thermal energy source, a commissioning act for the metering unit is drawn up and the metering unit is sealed. The seals are placed by representatives of the organization that owns the heat source and the main adjacent heat supply organization.

58. The metering unit is considered suitable for commercial metering of thermal energy and coolant from the date of signing the commissioning act.

59. If a non-compliance of the metering unit with the provisions of these Rules is detected, the metering unit is not put into operation and the commissioning report provides a complete list of identified deficiencies, indicating the paragraphs of these Rules, the provisions of which were violated, and the time frame for their elimination. Such a commissioning act is drawn up and signed by all members of the commission within 3 working days.

60. Before the start of the heating period, after the next inspection or repair, the readiness of the metering unit for operation is checked, about which a report on the periodic inspection of the metering unit at the heat energy source is drawn up in the manner established by paragraphs 53 - 59 of these Rules.

Commissioning of a metering unit installed at the consumer, on adjacent heating networks and on jumpers

61. The installed metering unit, which has undergone trial operation, is subject to commissioning.

62. Commissioning of a metering unit installed at the consumer is carried out by a commission consisting of the following:

A) representative of the heat supply organization;
b) consumer representative;
c) a representative of the organization that carried out the installation and commissioning of the metering unit being put into operation.

63. The commission is created by the owner of the accounting center.

64. To put the metering unit into operation, the owner of the metering unit submits to the commission a draft metering unit, agreed with the heat supply organization that issued the technical specifications and passport of the metering unit or a draft passport, which includes:

A) pipeline diagram (starting from the balance sheet boundary) indicating the length and diameters of pipelines, shut-off valves, instrumentation, mud traps, drains and jumpers between pipelines;
b) certificates of verification of instruments and sensors subject to verification, with valid verification marks;
c) a database of setting parameters entered into the measuring unit or heat calculator;
d) a sealing scheme for measuring instruments and equipment included in the metering unit, excluding unauthorized actions that violate the reliability of commercial metering of thermal energy and coolant;
e) hourly (daily) statements of continuous operation of the metering unit for 3 days (for objects with hot water supply - 7 days).

65. Documents for putting the metering unit into operation are submitted to the heat supply organization for consideration at least 10 working days before the expected day of commissioning.

66. When accepting a metering unit for operation, the commission checks:

A) compliance of the installation of the components of the metering unit with the design documentation, technical specifications and these Rules;
b) availability of passports, certificates of verification of measuring instruments, factory seals and brands;
c) compliance of the characteristics of measuring instruments with the characteristics specified in the passport data of the metering unit;
d) compliance of the measurement ranges of parameters allowed by the temperature schedule and the hydraulic operating mode of heating networks with the values ​​of the specified parameters determined by the contract and the conditions of connection to the heat supply system.

67. If there are no comments on the metering unit, the commission signs an act of commissioning the metering unit installed at the consumer.

68. The act of commissioning a metering unit serves as the basis for maintaining commercial accounting of thermal energy, coolant using metering devices, monitoring the quality of thermal energy and heat consumption modes using the received measurement information from the date of its signing.

69. When signing the act of commissioning the metering unit, the metering unit is sealed.

70. The metering unit is sealed:

A) a representative of the heat supply organization if the metering unit belongs to the consumer;
b) a representative of the consumer who has a metering unit installed.

71. Places and devices for sealing the metering unit are prepared in advance by the installation organization. The connection points of primary transducers, connectors of electrical communication lines, protective covers on the settings and adjustment controls of devices, power supply cabinets for devices and other equipment, interference with the operation of which may lead to distortion of measurement results, are subject to sealing.

72. If members of the commission have comments on the metering unit and identify deficiencies that impede the normal functioning of the metering unit, this metering unit is considered unsuitable for commercial metering of thermal energy and coolant.

In this case, the commission draws up a report on the identified deficiencies, which provides a complete list of identified deficiencies and the deadlines for their elimination. The specified act is drawn up and signed by all members of the commission within 3 working days. Re-acceptance of the metering unit into operation is carried out after complete elimination of the identified violations.

73. Before each heating season and after the next verification or repair of metering devices, the readiness of the metering unit for operation is checked, about which a periodic inspection report of the metering unit is drawn up at the interface of adjacent heating networks in the manner established by paragraphs 62 - 72 of these Rules.

Operation of a metering unit installed at a thermal energy source

74. The owner of the thermal energy source is responsible for the technical condition of measuring instruments and devices included in the metering units installed at the thermal energy source.

75. The metering unit is considered to be out of order in the following cases:

A) lack of measurement results;
b) unauthorized interference in the operation of the metering unit;
c) violation of the installed seals on measuring instruments and devices included in the metering unit, as well as damage to electrical communication lines;
d) mechanical damage to measuring instruments and devices included in the metering unit;
e) the presence of taps into pipelines not provided for in the design of the metering unit;
f) expiration of the verification period for any of the devices (sensors);
g) work exceeding normalized limits for most of the billing period.

76. The time of failure of the metering unit installed at the source of thermal energy is recorded by an entry in the log of meter readings.

77. The representative of the owner of the heat energy source is also obliged to report to the heating network organization and the unified heat supply organization data on the readings of metering devices at the time of their failure.

78. The owner of a thermal energy source is obliged to inform the consumer about the failure of the metering devices included in the metering unit, if metering is carried out using these metering devices that are part of the metering unit installed at the thermal energy source, and transfer to the consumer the data of the instrument readings at the time their failure.

79. Representatives of the heat supply organization and consumers (if metering is carried out using devices installed at the heat energy source) are given unhindered access to the metering unit and documentation related to the metering unit.

Operation of a metering unit installed by the consumer on adjacent heating networks and on jumpers

80. Within the period established by the contract, the consumer or his authorized person submits to the heat supply organization a heat consumption report signed by the consumer. The agreement may stipulate that the heat consumption report is submitted on paper, on electronic media, or using dispatch tools (using an automated information-measuring system).

81. The consumer has the right to demand, and the heat supply organization is obliged to provide him with, a calculation of the amount of consumed thermal energy and coolant for the reporting period no later than 15 days after submitting the heat consumption report.

82. If the metering unit belongs to a heat supply (heating network) organization, the consumer has the right to request copies of printouts from metering devices for the reporting period.

83. If there are reasons to doubt the reliability of the readings of metering devices, any party to the contract has the right to initiate a commission check of the functioning of the metering unit with the participation of the heat supply (heating network) organization and the consumer. The results of the commission’s work are documented in an act of checking the functioning of the metering unit.

84. If disagreements arise between the parties to the contract regarding the correctness of the readings of the metering unit, the owner of the metering unit, at the request of the other party to the contract, within 15 days from the date of application, organizes an extraordinary verification of the metering devices included in the metering unit, with the participation of a representative of the heat supply organization and the consumer.

85. If the accuracy of the meter readings is confirmed, the costs of an extraordinary verification are borne by the party to the contract that requested the extraordinary verification. If it is discovered that the meter readings are unreliable, the owner of the metering unit will bear the costs.

86. If irregularities in the operation of the metering unit are detected, the amount of thermal energy consumed is determined by the calculation method from the moment the metering device included in the metering unit fails. The time of failure of the metering device is determined from the heat meter archive data, and in their absence - from the date of submission of the last heat consumption report.

87. The owner of a metering unit is obliged to ensure:

A) unimpeded access to the accounting center for the party to the contract;
b) safety of installed metering units;
c) safety of seals on measuring instruments and devices included in the metering unit.

88. If the metering unit is installed in a premises that does not belong to the owner of the metering unit on the right of ownership or other legal basis, the owner of the premises bears the responsibilities provided for in paragraph 87 of these Rules.

89. If any violations are detected in the functioning of the metering unit, the consumer is obliged to notify the service organization and the heat supply organization about this within 24 hours and draw up an act signed by representatives of the consumer and the service organization. The consumer submits this act to the heat supply organization along with a report on heat consumption for the relevant period within the time frame specified in the contract.

90. If the consumer fails to timely report violations in the functioning of the metering unit, the calculation of the consumption of thermal energy and coolant for the reporting period is carried out by calculation.

91. At least once a year, as well as after the next (extraordinary) verification or repair, the functionality of the metering unit is checked, namely:

A) the presence of seals (stamps) of the verifier and the heat supply organization;
b) validity period of the verification;
c) operability of each measurement channel;
d) compliance with the permissible measurement range for the device metering the actual values ​​of the measured parameters;
e) compliance of the characteristics of the heat meter settings with the characteristics contained in the entered database.

92. The results of checking the metering unit are documented in acts signed by representatives of the heat supply organization and the consumer.

93. The assessment of the deviation of the quality indicators of heat supply and heat consumption from the values ​​specified in the contract is carried out on the basis of the readings of metering devices included in the metering unit installed at the consumer, or portable measuring instruments. The measuring instruments used must be verified. The lack of appropriate measurements serves as a basis for rejecting consumer claims regarding the quality of thermal energy and coolant.

III. Characteristics of thermal energy and coolant to be measured for the purposes of their commercial accounting and quality control of heat supply

94. Commercial accounting of thermal energy and coolant is subject to the amount of thermal energy used, including for hot water supply, the mass (volume) of the coolant, as well as the values ​​of quality indicators of thermal energy during its supply, transmission and consumption.

95. For the purpose of commercial accounting of thermal energy, coolant and quality control of heat supply, the following is measured:


b) pressure in the supply and return pipelines;
c) coolant temperatures in the supply and return pipelines (return water temperature in accordance with the temperature chart);
d) coolant flow in the supply and return pipelines;
e) coolant flow rate in the heating and hot water supply system, including the maximum hourly flow rate;
f) the flow rate of coolant used to recharge the heating system, if there is a make-up pipeline.

96. For the purpose of commercial accounting of thermal energy, coolant and quality control of heat supply at a source of thermal energy when using steam as a coolant, the following is measured:

A) operating time of metering unit devices in normal and abnormal modes;
b) supplied thermal energy per hour, day and billing period;
c) mass (volume) of steam released and condensate returned to the heat source per hour, day and calculation period;
d) temperatures of steam, condensate and cold water per hour and per day, followed by determination of their weighted average values;
e) steam and condensate pressure per hour and per day, followed by determination of their weighted average values.

97. In open and closed heat consumption systems at the heat energy and coolant metering unit, the following is determined using a device (devices):

A) mass (volume) of coolant received through the supply pipeline and returned through the return pipeline;
b) mass (volume) of coolant received through the supply pipeline and returned through the return pipeline for each hour;
c) average hourly and average daily temperature of the coolant in the supply and return pipelines of the metering unit.

98. In open and closed heat consumption systems, the total heat load of which does not exceed 0.1 Gcal/h, at the metering station using instruments, only the operating time of the metering unit devices, the mass (volume) of the received and returned coolant, as well as the mass (volume ) coolant consumed for make-up.

99. In heat consumption systems connected according to an independent circuit, the mass (volume) of coolant consumed for make-up is additionally determined.

100. In open heat consumption systems, the following are additionally defined:

A) mass (volume) of coolant used for water collection in hot water supply systems;
b) average hourly coolant pressure in the supply and return pipelines of the metering unit.

101. Average hourly and average daily values ​​of coolant parameters are determined based on the readings of instruments recording coolant parameters.

102. In steam systems, heat consumption at the metering station is determined using instruments:

A) mass (volume) of the resulting steam;
b) mass (volume) of the returned condensate;
c) mass (volume) of steam produced per hour;
d) hourly average temperature and steam pressure;
e) average hourly temperature of the returned condensate.

103. Average hourly values ​​of coolant parameters are determined based on the readings of instruments recording these parameters.

104. In heat consumption systems connected to heating networks according to an independent scheme, the mass (volume) of condensate consumed for make-up is determined.

Heat supply quality control

105. Quality control of heat supply during the supply and consumption of heat energy is carried out at the boundaries of the balance sheet between the heat supply, heating network organization and the consumer.

106. The quality of heat supply is defined as the set of thermal energy characteristics established by regulatory legal acts of the Russian Federation and (or) the heat supply agreement, including the thermodynamic parameters of the coolant.

107. The following parameters characterizing the thermal and hydraulic regime of the heat supply system of heat supply and heating network organizations are subject to quality control of heat supply:


pressure in the supply and return pipelines;
coolant temperature in the supply pipeline in accordance with the temperature schedule specified in the heat supply contract;

B) when connecting a consumer’s heat-consuming installation through a central heating point or when directly connecting to heating networks:

pressure difference at the outlet of the central heating point between the pressure in the supply and return pipelines;
compliance with the temperature schedule at the inlet of the heating system throughout the entire heating period;
pressure in the supply and circulation pipeline of hot water supply;
temperature in the supply and circulation pipelines of hot water supply;

B) when connecting a consumer’s heat-consuming installation through an individual heating point:
pressure in the supply and return pipelines;
compliance with the temperature schedule at the input of the heating network throughout the entire heating period.

108. The following parameters characterizing the thermal and hydraulic conditions of the consumer are subject to quality control of heat supply:

A) when connecting the consumer’s heat-consuming installation directly to the heating network:
return water temperature in accordance with the temperature schedule specified in the heat supply contract;
coolant flow rate, including the maximum hourly flow rate determined by the heat supply agreement;
make-up water consumption determined by the heat supply agreement;

B) when connecting a consumer’s heat-consuming installation through a central heating point, an individual heating point or when directly connecting to heating networks:
temperature of the coolant returned from the heating system in accordance with the temperature schedule;
coolant flow in the heating system;
make-up water consumption according to the heat supply agreement.

109. Specific values ​​of controlled parameters are indicated in the heat supply contract.

IV. The procedure for determining the amount of supplied thermal energy and coolant for the purpose of their commercial accounting, including by calculation

110. The amount of thermal energy and coolant supplied by a source of thermal energy, for the purpose of their commercial accounting, is defined as the sum of the amounts of thermal energy and coolant in each pipeline (supply, return and make-up).

111. The amount of thermal energy and coolant received by the consumer is determined by the energy supply organization based on the readings of the consumer’s metering devices for the billing period.

112. If, in order to determine the amount of supplied (consumed) thermal energy, coolant for the purpose of commercial accounting, it is necessary to measure the temperature of cold water at the source of thermal energy, it is allowed to enter the specified temperature into the computer in the form of a constant with periodic recalculation of the amount of consumed thermal energy taking into account the actual cold water temperature. It is allowed to introduce a zero cold water temperature throughout the year.

113. The value of the actual temperature is determined:

A) for the coolant - by a single heat supply organization based on data on the actual average monthly values ​​of the cold water temperature at the heat source, provided by the owners of the heat sources, which are the same for all consumers of heat within the boundaries of the heat supply system. The frequency of recalculation is determined in the contract;

B) for hot water - by the organization operating the central heating point, based on measurements of the actual cold water temperature in front of the hot water heaters. The frequency of recalculation is determined in the contract.

114. Determination of the amount of supplied (received) thermal energy, coolant for the purpose of commercial accounting of thermal energy, coolant (including by calculation) is carried out in accordance with the methodology for commercial accounting of thermal energy, coolant, approved by the Ministry of Construction and Housing and Communal Services of the Russian Federation (hereinafter referred to as the methodology). In accordance with the methodology, the following is carried out:

A) organization of commercial metering at the source of thermal energy, coolant and in heating networks;

B) determination of the amount of thermal energy and coolant for the purpose of their commercial accounting, including:

Amounts of thermal energy, coolant released by a source of thermal energy, coolant;
the amount of thermal energy and mass (volume) of coolant received by the consumer;
the amount of thermal energy and coolant consumed by the consumer during the absence of commercial metering of thermal energy and coolant according to metering devices;

C) determination of the amount of thermal energy, coolant by calculation for connection through a central heating point, individual heating point, from sources of thermal energy, coolant, as well as for other connection methods;

D) determination by calculation of the amount of thermal energy and coolant for non-contractual consumption of thermal energy;

D) determination of the distribution of losses of thermal energy and coolant;

E) when metering devices operate during an incomplete billing period, adjust the thermal energy consumption by calculation for the period of absence of readings in accordance with the methodology.

115. If there are no metering devices at the metering points or the operation of metering devices for more than 15 days of the billing period, the determination of the amount of thermal energy spent on heating and ventilation is carried out by calculation and is based on the recalculation of the base indicator for the change in outside air temperature for the entire billing period.

116. The value of the heat load specified in the heat supply contract is taken as the base indicator.

117. The base indicator is recalculated based on the actual average daily outside air temperature for the calculation period, taken according to meteorological observations of the weather station of the territorial executive body closest to the heat consumption facility, which carries out the functions of providing public services in the field of hydrometeorology.

If, during the period of cutting the temperature graph in the heating network at positive outside temperatures, there is no automatic control of the heat supply for heating, and also if the cutting of the temperature graph is carried out during a period of low outdoor temperatures, the value of the outside air temperature is taken equal to the temperature indicated at the beginning of the cut graphics. When automatically regulating the heat supply, the actual temperature value indicated at the beginning of the graph cutting is taken.

118. In the event of a malfunction of metering devices, the expiration of their verification period, including removal from work for repair or verification for up to 15 days, the average daily amount of thermal energy and coolant determined from the metering devices over time is taken as the base indicator for calculating thermal energy and coolant normal operation during the reporting period, reduced to the calculated outside air temperature.

119. If the deadlines for submitting instrument readings are violated, the amount of thermal energy and coolant determined by metering devices for the previous billing period, reduced to the calculated outside air temperature, is taken as the average daily indicator.

If the previous billing period falls on a different heating period or there is no data for the previous period, the amount of thermal energy and coolant is recalculated in accordance with paragraph 121 of these Rules.

120. The amount of thermal energy and coolant spent on hot water supply, in the presence of separate metering and temporary malfunction of devices (up to 30 days), is calculated based on the actual consumption determined by metering devices for the previous period.

121. In the absence of separate metering or inoperative condition of the devices for more than 30 days, the amount of thermal energy and coolant spent on hot water supply is assumed to be equal to the values ​​​​established in the heat supply contract (the amount of heat load on hot water supply).

122. When determining the amount of thermal energy and coolant, the amount of thermal energy supplied (received) in the event of emergency situations is taken into account. Emergency situations include:

A) operation of the heat meter at coolant flow rates below the minimum or above the maximum limit of the flow meter;
b) operation of the heat meter when the coolant temperature difference is below the minimum value established for the corresponding heat meter;
c) functional failure;
d) changing the direction of coolant flow, unless such a function is specifically included in the heat meter;
e) lack of power supply to the heat meter;
f) lack of coolant.

123. The following periods of abnormal operation of metering devices must be determined in the heat meter:

A) the duration of any malfunction (accident) of measuring instruments (including a change in the direction of coolant flow) or other devices of the metering unit that make it impossible to measure thermal energy;
b) time of power failure;
c) time of absence of water in the pipeline.

124. If the heat meter has a function for determining the time during which there is no water in the pipeline, the time of absence of water is allocated separately and the amount of thermal energy for this period is not calculated. In other cases, the time of lack of water is included in the duration of the emergency situation.

125. The amount of coolant (thermal energy) lost due to a leak is calculated in the following cases:

A) a leak, including a leak on consumer networks up to the metering station, has been identified and documented in joint documents (bilateral acts);
b) the amount of leakage recorded by the water meter when feeding independent systems exceeds the standard.

126. In the cases specified in paragraph 125 of these Rules, the leakage value is determined as the difference in the absolute values ​​of the measured values ​​without taking into account errors.

In other cases, the amount of coolant leakage determined in the heat supply contract is taken into account.

127. The mass of the coolant consumed by all consumers of thermal energy and lost in the form of leakage in the entire heat supply system from the thermal energy source is defined as the mass of the coolant consumed by the thermal energy source to recharge all pipelines of water heating networks, minus intra-station expenses for own needs during production electrical energy and in the production of thermal energy, for the production and economic needs of the objects of this source and intra-station technological losses by pipelines, units and devices within the boundaries of the source.

V. The procedure for distributing losses of thermal energy and coolant between heating networks in the absence of metering devices at the boundaries of adjacent heating networks

128. The distribution of losses of thermal energy, coolant, as well as the amount of thermal energy, coolant transferred between heating networks of heat supply organizations and heating network organizations in the absence of metering devices at the boundaries of adjacent parts of heating networks, is carried out by calculation as follows:

A) in relation to thermal energy transferred (received) at the border of the balance sheet of adjacent heating networks, the calculation is based on the balance of the amount of thermal energy supplied to the heating network and consumed by heat consuming installations of consumers (for all owner organizations and (or) other legal owners of adjacent heating networks) for all sections of pipelines at the border(s) of the balance sheet of adjacent sections of the heating network, taking into account heat energy losses associated with emergency leaks and technological losses (pressure testing, testing), losses through damaged thermal insulation in adjacent heating networks, which are documented in acts , standards for technological losses during the transfer of thermal energy and losses exceeding the approved values ​​(excessive losses);

B) in relation to the coolant transferred at the border of the balance sheet of adjacent heating networks, the calculation is based on the balance of the amount of coolant supplied to the heating network and consumed by heat-consuming installations of consumers, taking into account coolant losses associated with emergency coolant leaks, documented in acts, standards for technological losses during transfer of thermal energy approved in accordance with the established procedure, and losses exceeding the approved values ​​(exceeding norms).

129. The distribution of excess losses of thermal energy and coolant between adjacent heating networks is carried out in quantities proportional to the values ​​of the approved standards for technological losses and losses of thermal energy, taking into account emergency leaks of coolant through damaged thermal insulation.

130. In the case of transfer of thermal energy, coolant through a section of the heating network owned by the consumer, when distributing losses of thermal energy, coolant and excess losses of thermal energy, coolant, the specified heating networks are considered as adjacent heating networks.

According to the text published on the Official Portal of draft regulatory legal acts, it is proposed to introduce new Rules for the commercial metering of heat and coolant and invalidate the Decree of the Government of the Russian Federation of November 18, 2013 No. 1034 “On commercial metering of heat energy and coolant.”

You can read the text of the project and write your review about it using this link:

In the text of the new Rules, the Ministry of Construction fixed a list of the main parameters recorded by heat and coolant metering devices:

a) the time of normal and faulty operation of the metering unit during the day;

b) coolant temperature in the supply and return pipelines;

c) coolant flow in the supply and/or return pipelines;

d) the amount of coolant entering the hot water supply system for open heating systems;

e) the amount of water and thermal energy entering the hot water supply system with a separate input (from the central heating point);

f) the volume of coolant used to recharge the heat supply system (if there is a make-up pipeline);

g) coolant pressure in the supply and return pipelines (when installing pressure sensors);

h) the temperature of the coolant used for make-up at the thermal energy source before the point of insertion of the make-up pipeline into the heating network.

In this regard, the following basic requirements for heat metering devices have been established:

1) Metering devices must be sealed so that no one can interfere with their operation. Along with sealing the structure, it is possible to protect measuring instruments by entering a password.

2) The components of a heat meter are a computer and instruments for measuring flow (volume), temperature, and for steam heat supply systems, a pressure sensor. Pressure measuring instruments used in water heating systems are used only for the purpose of monitoring the quality of the coolant.

3) The computer (calculation converter) must be equipped with a standard industrial protocol and interface that allows remote data collection. Remote collection should not affect the metrological characteristics of the heat meter.

4) Measuring instruments that have settings must have non-volatile memory that allows you to save the current settings and their changes. The computer must additionally store in non-volatile memory an archive of measured data, an event log, including emergency situations, and be able to check the settings using standard tools or external devices and remote access tools.

5) The settings are entered into the settings card, which is drawn up in the passport of the measuring instrument or as a separate document in the project of the metering unit. Any changes to the settings must be recorded in the event log of the measuring instrument.

6) In the case of using automated measuring metering systems, instead of calculators (heat meters), data collection and transmission controllers (calculation converters), which are measuring instruments of approved types, can be used. In this case, the measured parameters are calculated by the automated system itself.

Also, the project describes the principles of design, placement and commissioning of commercial heat metering devices.

Compared to the current Decree of the Government of the Russian Federation No. 1034 of November 18, 2013, in this draft resolution:

the sequence of sections of the Rules has been changed to ensure consistency in the organization of commercial accounting of thermal energy and coolant;

the provision defining its scope of application has been changed (clause 1 of the Rules);

additions and clarifications have been made to a number of concepts used (clause 3 of the Rules);

the conditions for the use of metering devices during the 3-year transition period have been specified (in accordance with paragraphs 6 and 7 of the Rules);

clauses providing for the use of cold water temperature at the source of thermal energy to adjust the amount of thermal energy received by consumers have been excluded, since this contradicts the provisions of the current Pricing Fundamentals in the field of heat supply, approved by Decree of the Government of the Russian Federation of October 22, 2012 No. 1075 and distorts the true value of the quantity consumed thermal energy. The temperature of cold water at the source should be measured and taken into account exclusively when determining the amount of own costs and when setting the tariff for supplied thermal energy and coolant.

In accordance with the Federal Law "On Heat Supply", the Government of the Russian Federation decides:

1. Approve the attached Rules for commercial metering of thermal energy and coolant.

2. Federal executive authorities must bring their regulatory legal acts into compliance with this resolution within 3 months.

3. The Ministry of Construction and Housing and Communal Services of the Russian Federation must approve within 2 weeks the methodology for commercial accounting of thermal energy and coolant.

Chairman of the Government of the Russian Federation

D.Medvedev


Approved by decree of the Government of the Russian Federation
dated November 18, 2013 No. 1034

Rules for commercial metering of thermal energy and coolant

I. General provisions

1. These Rules establish the procedure for organizing commercial metering of thermal energy and coolant, including:

a) requirements for metering devices;

b) characteristics of thermal energy, coolant, subject to measurement for the purpose of commercial accounting of thermal energy, coolant and quality control of heat supply;

c) the procedure for determining the amount of supplied thermal energy and coolant for the purpose of commercial accounting of thermal energy and coolant (including by calculation);

d) the procedure for distributing losses of thermal energy and coolant by heating networks in the absence of metering devices at the boundaries of adjacent heating networks.

2. The methodology for commercial accounting of thermal energy and coolant is determined by the methodology approved by the Ministry of Construction and Housing and Communal Services of the Russian Federation (hereinafter referred to as the methodology).

3. The terms used in these Rules mean the following:

"commissioning of a metering unit"- procedure for checking the compliance of the thermal energy metering unit with the requirements of regulatory legal acts and design documentation, including drawing up a commissioning report for the thermal energy metering unit;

"water meter"- a measuring device designed to measure the volume (mass) of water (liquid) flowing in a pipeline through a section perpendicular to the direction of flow velocity;

"operating time of metering devices"- the time interval during which, based on the readings of metering devices, thermal energy is recorded, as well as the mass (volume) and temperature of the coolant are measured and recorded;

"heating network output"- output of heating networks from a source of thermal energy in a certain direction;

"calculator"- a component of a heat meter that receives signals from sensors and provides calculation and accumulation of data on the amount of thermal energy and coolant parameters;

"dependent connection diagram of a heat-consuming installation"- diagram of connecting the heat-consuming installation to the heating network, in which the coolant from the heating network flows directly into the heat-consuming installation;

"closed water heating system"– a complex of technologically interconnected engineering structures designed for heat supply without extracting hot water (coolant) from the heating network;

"measuring accounting system"- a multi-channel measuring instrument, including channels for measuring thermal energy with measuring components - heat meters, as well as additional measuring channels for the mass (volume) of the coolant and its parameters - temperature and pressure;

"individual heating point"- a set of devices for connecting a heat-consuming installation to a heating network, converting coolant parameters and distributing it by type of heat load for one building, structure or structure;

"thermal energy quality"- a set of parameters (temperatures and pressures) of the coolant used in the processes of production, transmission and consumption of thermal energy, ensuring the suitability of the coolant for the operation of heat-consuming installations in accordance with their purpose;

"saturated steam" - water vapor that is in thermodynamic equilibrium with water in contact with it;

"independent connection diagram for a heat-consuming installation"- diagram of connecting the heat-consuming installation to the heating network, in which the coolant coming from the heating network passes through a heat exchanger installed at the heating point, where it heats the secondary coolant, which is subsequently used in the heat-consuming installation;

"malfunction of measuring instruments of the metering unit"- the state of measuring instruments in which the metering unit does not comply with the requirements of regulatory legal acts, normative-technical and (or) design (project) documentation (including due to the expiration of the verification period for measuring instruments included in the metering unit, violation of installed seals , as well as with work in emergency situations);

"open water heating system"- a set of technologically interconnected engineering structures designed for heat supply and (or) hot water supply by extracting hot water (coolant) from the heating network or extracting hot water from hot water supply networks;

"superheated steam"- water vapor having a temperature higher than the saturation temperature at a certain pressure;

"recharge"- coolant, additionally supplied to the heat supply system to replenish its technological consumption and losses during the transfer of thermal energy;

"metering device"- a measuring instrument, including technical devices that perform the functions of measuring, accumulating, storing and displaying information about the amount of thermal energy, as well as mass (volume), temperature, coolant pressure and operating time of devices;

"coolant flow"- mass (volume) of coolant passing through the cross-section of the pipeline per unit of time;

"flow meter"- a device designed to measure coolant flow;

"calculation method"- a set of organizational procedures and mathematical actions to determine the amount of thermal energy and coolant in the absence of metering devices or their inoperability, used in the cases established by these Rules;

"temperature graph cut"- maintaining a constant temperature of the coolant in the heating network, regardless of the outside air temperature;

"heat meter"- a device designed to measure the thermal energy emitted by the coolant or consumed together with it, which is a single structure or consisting of component elements - flow converters, flow meters, water meters, temperature (pressure) sensors and a computer;

"technical operation of the metering unit"- a set of operations for maintenance and repair of elements of a thermal energy metering unit, ensuring the reliability of measurement results;

"accounting unit"- a technical system consisting of measuring instruments and devices that provide accounting for thermal energy, mass (volume) of the coolant, as well as monitoring and recording the parameters of the coolant;

"coolant leak"- loss of water (steam) through leaks in process equipment, pipelines and heat-consuming installations;

"Measurement accounting system form"- a document drawn up in relation to the measuring system of the metering unit and reflecting, among other things, the composition of the metering unit and changes in its composition;

"functional failure"- a malfunction in the system of the metering unit or its elements, in which the metering of thermal energy, mass (volume) of the coolant stops or becomes unreliable;

"central heating point"- a set of devices for connecting heat-consuming installations of several buildings, structures or structures to the heating network, as well as for converting the parameters of the coolant and distributing it by type of heat load.

4. Commercial accounting of thermal energy and coolant is organized for the purposes of:

a) carrying out settlements between heat supply, heating network organizations and consumers of thermal energy;

b) control over the thermal and hydraulic operating conditions of heat supply systems and heat-consuming installations;

c) control over the rational use of thermal energy and coolant;

d) documenting coolant parameters - mass (volume), temperature and pressure.

5. Commercial metering of thermal energy and coolant is carried out using metering devices that are installed at the metering point located on the border of the balance sheet, if a heat supply agreement, a contract for the supply of thermal energy (power), coolant or a contract for the provision of services for the transfer of thermal energy and coolant ( hereinafter referred to as the agreement) no other accounting point has been determined.

6. Metering units put into operation before the entry into force of these Rules can be used for commercial metering of thermal energy and coolant until the expiration of the service life of the main metering devices (flow meter, heat calculator) included in the metering units.

7. After 3 years from the date of entry into force of these Rules, heat meters that do not meet the requirements of these Rules cannot be used for installation in both new and existing metering units.

8. Heat supply organizations or other persons do not have the right to require the consumer of thermal energy to install devices or additional devices at the metering station that are not provided for by these Rules.

9. The heat supply organization, heating network organization and consumer have the right to install additional devices at the metering station to control the supply and consumption of thermal energy, coolant, including for remote readings from the heat meter, without interfering with the commercial metering of heat energy, coolant and other affecting the accuracy and quality of measurements.

10. If remote reading equipment is installed at the metering station, the heat supply (heating network) organization and the consumer have the right to gain access to the specified system in the manner and on the terms determined by the contract.

11. If a single thermal energy consumer is connected to the heating network emanating from a source of thermal energy and this heating network belongs to the specified thermal energy consumer by right of ownership or other legal basis, by agreement of the parties to the contract it is allowed to keep records of the consumed thermal energy according to the readings of the device metering installed at the metering unit for the thermal energy source.

12. If one of the parties to the contract, obligated in accordance with federal laws to install a metering device, does not fulfill this obligation, the other party to the contract is obliged, in the manner established by the legislation of the Russian Federation, to install a metering device to make payments under the contract.

13. If both parties to the contract have installed a metering device, for commercial metering of thermal energy and coolant under the contract, the readings of the metering device that is installed at the balance sheet boundary are used.

If there are 2 equivalent metering units on opposite sides of the balance sheet boundary, for commercial metering of thermal energy and coolant, the readings of the metering unit are taken, providing metering with a minimum error. The error in this case consists of the amount of unmeasured heat losses from the balance sheet boundary to the metering unit and the reduced measurement error.

14. The metering devices used must comply with the requirements of the legislation of the Russian Federation on ensuring the uniformity of measurements in force at the time the metering devices are put into operation.

After the interval between verifications has expired or after the metering devices fail or are lost, if this happened before the expiration of the inter-verification interval, metering devices that do not comply with the requirements of the legislation of the Russian Federation on ensuring the uniformity of measurements are subject to verification or replacement with new metering devices.

15. Commercial metering of thermal energy and coolant is organized at all delivery and reception points.

16. Commercial accounting of thermal energy and coolant supplied to consumers of thermal energy and coolant can be organized by both heat supply organizations, heating network organizations, and consumers of thermal energy.

17. Organization of commercial accounting of thermal energy and coolant, unless otherwise provided by the provisions of these Rules, includes:

a) obtaining technical specifications for the design of a metering unit;

b) design and installation of metering devices;

c) commissioning of a metering unit;

d) operation of metering devices, including the procedure for regularly taking meter readings and using them for commercial metering of thermal energy and coolant;

e) verification, repair and replacement of metering devices.

18. Issuance of technical specifications for the installation of a metering unit (device), commissioning, sealing of metering units (devices) and participation in commissions for the acceptance of metering units (devices) is carried out without charging a fee to the thermal energy consumer.

19. Metering units are installed in a place as close as possible to the boundary of the pipelines’ balance sheet, taking into account the real possibilities at the facility.

20. At thermal energy sources, metering units are installed at each outlet of the heating network.

21. The selection of thermal energy and coolant for the own and economic needs of the thermal energy source is organized up to the metering units at the terminals. In other cases, the selection of thermal energy and coolant must be carried out through separate metering units.

The selection of coolant for replenishment of heat supply systems with the installation of a separate meter is carried out from the return pipeline after the flow sensor along the flow of the coolant. Pressure sensors can be installed both before and after the flow sensor. Temperature sensors are installed after the flow sensor along the coolant flow.

22. If sections of the heating network belong on the right of ownership or other legal basis to different persons, or if there are jumpers between heating networks that belong on the right of ownership or other legal basis to different persons, metering units must be installed at the border of the balance sheet.

23. Collection of information about the readings of metering devices, the amount of supplied (received, transported) thermal energy, coolant, the amount of thermal energy in the supplied (received, transported) hot water, the number and duration of violations that occur in the operation of metering devices, and other information provided for in the technical documentation, displayed by metering devices, as well as taking readings from metering devices (including using telemetric systems - remote reading systems) are carried out by the consumer or the heating network organization, unless otherwise provided by the agreement with the heat supply organization.

24. The consumer or heating network organization provides the organization providing water supply and (or) sanitation, before the end of the 2nd day of the month following the billing month, information on the readings of metering devices as of the 1st day of the month following the billing month, if other deadlines are not established by the legislation of the Russian Federation, as well as information about current readings of metering devices within 2 business days after receiving a request for such information from the heat supply organization. Such information is sent to the heat supply organization in any available way (postal mail, fax, telephone message, electronic message using the Internet), allowing confirmation of receipt of the specified information by the heat supply organization.

If the technical characteristics of the metering devices and metering units used allow the use of telemetric systems for transmitting meter readings and there is financial and technical support for the installation of telemetric modules and telemetric software, the presentation (taking) of meter readings is carried out remotely using such telemetric systems.

25. The consumer or heating network organization is obliged to ensure unimpeded access for representatives of the heat supply organization or, at the direction of the heat supply organization, representatives of another organization to metering units and metering devices to verify the readings of metering devices and check compliance with the operating conditions of the metering unit devices.

26. If, during the reconciliation process, a discrepancy is found in the information about the readings of the metering devices of the consumer or heating network organization regarding the volume of supplied (received) heat energy, coolant with the information provided by the consumer or heating network organization, the heat supply organization draws up a reconciliation report of the readings of the metering devices, signed by representatives consumer or heating network organization and heat supply organization.

If the representative of the consumer or heating network organization does not agree with the contents of the act of reconciling meter readings, the representative of the consumer or heating network organization marks the act as “acquainted” and affixes a signature. Objections of the consumer or heating network organization are indicated in the act or sent to the heat supply organization in writing in any way that allows confirmation of receipt of the document by the consumer or heating network organization. If a representative of a consumer or heating network organization refuses to sign the act of reconciling meter readings, such act is signed by a representative of the heat supply organization with the note “the representative of the consumer or heating network organization refused to sign.”

The act of reconciling meter readings is the basis for recalculating the volume of supplied (received) heat energy and coolant from the day of signing the act of reconciling meter readings until the day of signing the next act.

27. In order to control the volumes of supplied (received) heat energy and coolant, the heat supply organization or consumer or heating network organization has the right to use control (parallel) metering devices, provided that one of the parties to the contract notifies the other party to the contract about the use of such metering devices.

Control (parallel) metering devices are installed on the networks of the heat supply organization, heating network organization or consumer in places that allow commercial metering of heat energy, coolant supplied to the consumer, heating network organization.

If the readings of the control (parallel) metering devices and the main metering devices differ by more than the measurement error of such metering devices for a period of at least one billing month, the person who installed the control (parallel) metering device may require the other party to carry out extraordinary accounting verification of the metering device operated by this party.

28. The readings of the control (parallel) metering device are used for the purpose of commercial metering of thermal energy, coolant for the period of malfunction, verification of the main metering device, as well as in case of violation of the deadlines for submitting metering readings.

29. Installation, replacement, operation and verification of control (parallel) metering devices are carried out in accordance with the procedures provided for installation, replacement, operation and verification of main metering devices.

30. The person who installed the control (parallel) metering device is obliged to provide the other party to the contract (consumer, heating network organization, heat supply organization) with unhindered access to the control (parallel) metering devices in order to monitor the correct installation and operation of the control (parallel) metering device.

31. Commercial accounting of thermal energy and coolant by calculation is allowed in the following cases:

a) absence of metering devices at metering points;

b) malfunction of the meter;

c) violation of the deadlines established by the contract for submitting readings from metering devices that are the property of the consumer.

32. In case of non-contractual consumption of thermal energy and coolant, the amount of thermal energy and coolant used by the consumer is determined by calculation.

II. Requirements for metering devices

33. The metering unit is equipped with heat meters and metering devices, the types of which are included in the Federal Information Fund for Ensuring the Uniformity of Measurements.

34. A heat meter consists of flow and temperature (pressure) sensors, a calculator or a combination thereof. When measuring superheated steam, a steam pressure sensor is additionally installed.

Heat meters are equipped with standard industrial protocols and can be equipped with interfaces that allow remote data collection in an automatic (automated) mode. These connections should not affect the metrological characteristics of the heat meter.

If the data determined remotely and the data read directly from the heat meter do not match, the basis for determining the payment amount is the data read directly from the heat meter.

35. The design of heat meters and metering devices included in the heat meters ensures limited access to their parts in order to prevent unauthorized settings and interference, which can lead to distortion of measurement results.

36. In heat meters, correction of the internal clock of the calculator is allowed without opening the seals.

37. The heat meter calculator must have an indelible archive in which the main technical characteristics and adjustment coefficients of the device are recorded. Archive data is displayed on the device display and (or) computer. The adjustment coefficients are entered into the device passport. Any changes must be recorded in the archive.

Design of metering units

38. For a thermal energy source, the design of a metering unit measuring system is developed on the basis of a technical specification prepared by the owner of the thermal energy source and agreed with the adjacent heat supply (heating network) organization in terms of compliance with the requirements of these Rules, the terms of the contract and the conditions for connecting the thermal energy source to the heat supply system.

39. The design of a metering unit for objects other than thermal energy sources is developed on the basis of:

a) technical conditions issued by the heat supply organization at the request of the consumer;

b) the requirements of these Rules;

c) technical documentation for metering devices and measuring instruments.

40. Specifications contain:

a) name and location of the consumer;

c) calculated parameters of the coolant at the point of delivery;

d) temperature graph of coolant supply depending on the outside air temperature;

e) requirements for ensuring the ability to connect the metering unit to the system for remote reading of the metering device using standard industrial protocols and interfaces, with the exception of requirements for installing communication means if the heat supply organization uses or plans to use such means;

f) recommendations regarding measuring instruments installed at the metering station (the heat supply organization does not have the right to impose specific types of metering devices on the consumer, but for the purpose of unification and the possibility of organizing remote collection of information from the metering station, it has the right to make recommendations).

41. The heat supply organization is obliged to issue technical specifications for the installation of a metering device within 15 working days from the date of receipt of the consumer’s request.

42. If within the specified period the heat supply organization does not issue technical specifications or issues technical specifications that do not contain the information established by these Rules, the consumer has the right to independently develop a design for a metering unit and install the metering device in accordance with these Rules, of which he is obliged to notify heating supply organization.

43. If there is a ventilation and process heat load, the technical conditions are accompanied by an operating schedule and calculation of the power of heat-consuming installations.

44. The metering unit project contains:

a) a copy of the heat supply agreement with attached statements of delineation of balance sheet ownership and information on design loads for existing facilities. For newly commissioned facilities, information about design loads or connection conditions is attached;

b) plan for connecting the consumer to the heating network;

c) schematic diagram of a heating point with a metering unit;

d) plan of the heating point indicating the installation locations of sensors, placement of metering devices and cable wiring diagrams;

e) electrical and wiring diagrams for connecting metering devices;

f) a configuration database entered into the heat meter (including when switching to summer and winter operating modes);

g) a scheme for sealing measuring instruments and devices included in the metering unit, in accordance with paragraph 71 of these Rules;

h) formulas for calculating thermal energy and coolant;

i) coolant flow rate for heat-consuming installations by hour of the day in winter and summer;

j) for metering units in buildings (optional) - a table of daily and monthly heat energy consumption for heat-consuming installations;

k) forms of reporting sheets of meter readings;

l) wiring diagrams for installing flow meters, temperature sensors and pressure sensors;

m) specification of the equipment and materials used.

45. The diameter of the flow meters is selected in accordance with the calculated thermal loads so that the minimum and maximum coolant flow rates do not go beyond the normalized range of the flow meters.

46. ​​Drain devices (drainers) are provided:

a) on the supply pipeline - after the primary coolant flow converter;

b) on the return (circulation) pipeline - to the primary coolant flow converter.

48. The equipment set includes mounting inserts for replacing primary coolant flow converters and flow meters.

49. The design of a metering unit installed at a thermal energy consumer is subject to agreement with the heat supply (heating network) organization that issued the technical specifications for the installation of metering devices.

50. The consumer sends a copy of the metering unit design to the heat supply (heating network) organization for approval. If the metering unit project does not comply with the provisions of paragraph 44 of these Rules, the heat supply (heating network) organization is obliged, within 5 working days from the date of receipt of a copy of the metering unit project, to send a notification to the consumer about the provision of the missing documents (information).

In this case, the deadline for receipt of the metering unit project for approval is determined from the date of submission of the revised project.

51. The heat supply (heating network) organization does not have the right to refuse to approve the metering unit project if it complies with paragraph 44 of these Rules. In case of failure to provide information on approval or comments on the metering unit project within 15 working days from the date of receipt of a copy of the metering unit project, the project is considered approved.

Commissioning of a metering unit installed at a thermal energy source

52. Installed metering units (measuring systems of metering units), which have undergone trial operation, are subject to commissioning.

53. To commission the metering unit installed at the thermal energy source, the owner of the thermal energy source appoints a commission for commissioning the metering unit (hereinafter referred to as the commission) consisting of the following:

a) representative of the owner of the thermal energy source;

b) a representative of an adjacent heating network organization;

c) a representative of the organization carrying out installation and commissioning of the equipment being commissioned.

54. The representatives specified in paragraph 53 of these Rules are called by the owner of the thermal energy source no later than 10 working days before the day of expected acceptance by sending written notifications to the members of the commission.

55. To put the metering unit into operation, the owner of the thermal energy source submits to the commission:

a) schematic diagrams for connecting the terminals of the thermal energy source;

b) acts of delimitation of balance sheet ownership;

c) projects of metering units agreed upon by the heat supply (heating network) organization in the manner established by these Rules;

d) factory passports of the components of the metering unit, containing technical and metrological characteristics;

e) certificates of verification of instruments and sensors subject to verification, with valid verification marks;

f) form of the measuring system of the metering unit (if such a system is available);

g) the installed system, including instruments that record coolant parameters;

h) a statement of continuous operation of devices for 3 days.

56. When putting the metering unit into operation, the following is checked:

a) compliance of the serial numbers of measuring instruments with the numbers indicated in their passports;

b) compliance of the measurement ranges of parameters allowed by the temperature schedule and the hydraulic operating mode of heating networks with the values ​​of the specified parameters determined by the contract and the conditions of connection to the heat supply system;

c) the quality of installation of measuring instruments and communication lines, as well as compliance of installation with the requirements of technical and design documentation;

d) the presence of seals from the manufacturer or repair company and the verifier.

57. When commissioning the measuring system of a metering unit at a thermal energy source, a commissioning act for the metering unit is drawn up and the metering unit is sealed. The seals are placed by representatives of the organization that owns the heat source and the main adjacent heat supply organization.

58. The metering unit is considered suitable for commercial metering of thermal energy and coolant from the date of signing the commissioning act.

59. If a non-compliance of the metering unit with the provisions of these Rules is detected, the metering unit is not put into operation and the commissioning report provides a complete list of identified deficiencies, indicating the paragraphs of these Rules, the provisions of which were violated, and the time frame for their elimination. Such a commissioning act is drawn up and signed by all members of the commission within 3 working days.

60. Before the start of the heating period, after the next inspection or repair, the readiness of the metering unit for operation is checked, about which a report on the periodic inspection of the metering unit at the heat energy source is drawn up in the manner established by paragraphs 53 - 59 of these Rules.

Commissioning of a metering unit installed at the consumer, on adjacent heating networks and on jumpers

61. The installed metering unit, which has undergone trial operation, is subject to commissioning.

62. Commissioning of a metering unit installed at the consumer is carried out by a commission consisting of the following:

a) a representative of the heat supply organization;

b) consumer representative;

c) a representative of the organization that carried out the installation and commissioning of the metering unit being put into operation.

63. The commission is created by the owner of the accounting center.

64. To put the metering unit into operation, the owner of the metering unit submits to the commission a draft metering unit, agreed with the heat supply organization that issued the technical specifications and passport of the metering unit or a draft passport, which includes:

a) a diagram of pipelines (starting from the balance sheet boundary) indicating the length and diameters of pipelines, shut-off valves, instrumentation, mud traps, drains and jumpers between pipelines;

b) certificates of verification of instruments and sensors subject to verification, with valid verification marks;

c) a database of setting parameters entered into the measuring unit or heat calculator;

d) a sealing scheme for measuring instruments and equipment included in the metering unit, excluding unauthorized actions that violate the reliability of commercial metering of thermal energy and coolant;

e) hourly (daily) statements of continuous operation of the metering unit for 3 days (for objects with hot water supply - 7 days).

65. Documents for putting the metering unit into operation are submitted to the heat supply organization for consideration at least 10 working days before the expected day of commissioning.

66. When accepting a metering unit for operation, the commission checks:

a) compliance of the installation of the components of the metering unit with the design documentation, technical specifications and these Rules;

b) availability of passports, certificates of verification of measuring instruments, factory seals and brands;

c) compliance of the characteristics of measuring instruments with the characteristics specified in the passport data of the metering unit;

d) compliance of the measurement ranges of parameters allowed by the temperature schedule and the hydraulic operating mode of heating networks with the values ​​of the specified parameters determined by the contract and the conditions of connection to the heat supply system.

67. If there are no comments on the metering unit, the commission signs an act of commissioning the metering unit installed at the consumer.

68. The act of commissioning a metering unit serves as the basis for maintaining commercial accounting of thermal energy, coolant using metering devices, monitoring the quality of thermal energy and heat consumption modes using the received measurement information from the date of its signing.

69. When signing the act of commissioning the metering unit, the metering unit is sealed.

70. The metering unit is sealed:

a) a representative of the heat supply organization if the metering unit belongs to the consumer;

b) a representative of the consumer who has a metering unit installed.

71. Places and devices for sealing the metering unit are prepared in advance by the installation organization. The connection points of primary transducers, connectors of electrical communication lines, protective covers on the settings and adjustment controls of devices, power supply cabinets for devices and other equipment, interference with the operation of which may lead to distortion of measurement results, are subject to sealing.

72. If members of the commission have comments on the metering unit and identify deficiencies that impede the normal functioning of the metering unit, this metering unit is considered unsuitable for commercial metering of thermal energy and coolant.

In this case, the commission draws up a report on the identified deficiencies, which provides a complete list of identified deficiencies and the deadlines for their elimination. The specified act is drawn up and signed by all members of the commission within 3 working days. Re-acceptance of the metering unit into operation is carried out after complete elimination of the identified violations.

73. Before each heating season and after the next verification or repair of metering devices, the readiness of the metering unit for operation is checked, about which a report on the periodic inspection of the metering unit at the interface of adjacent heating networks is drawn up in the manner established by paragraphs 62-72 of these Rules.

Operation of a metering unit installed at a thermal energy source

74. The owner of the thermal energy source is responsible for the technical condition of measuring instruments and devices included in the metering units installed at the thermal energy source.

75. The metering unit is considered to be out of order in the following cases:

a) lack of measurement results;

b) unauthorized interference in the operation of the metering unit;

c) violation of the installed seals on measuring instruments and devices included in the metering unit, as well as damage to electrical communication lines;

d) mechanical damage to measuring instruments and devices included in the metering unit;

e) the presence of taps into pipelines not provided for in the design of the metering unit;

f) expiration of the verification period for any of the devices (sensors);

g) work exceeding normalized limits for most of the billing period.

76. The time of failure of the metering unit installed at the source of thermal energy is recorded by an entry in the log of meter readings.

77. The representative of the owner of the heat energy source is also obliged to report to the heating network organization and the unified heat supply organization data on the readings of metering devices at the time of their failure.

78. The owner of a thermal energy source is obliged to inform the consumer about the failure of the metering devices included in the metering unit, if metering is carried out using these metering devices that are part of the metering unit installed at the thermal energy source, and transfer to the consumer the data of the instrument readings at the time their failure.

79. Representatives of the heat supply organization and consumers (if metering is carried out using devices installed at the heat energy source) are given unhindered access to the metering unit and documentation related to the metering unit.

Operation of a metering unit installed by the consumer on adjacent heating networks and on jumpers

80. Within the period established by the contract, the consumer or his authorized person submits to the heat supply organization a heat consumption report signed by the consumer. The agreement may stipulate that the heat consumption report is submitted on paper, on electronic media, or using dispatch tools (using an automated information-measuring system).

81. The consumer has the right to demand, and the heat supply organization is obliged to provide him with, a calculation of the amount of consumed thermal energy and coolant for the reporting period no later than 15 days after submitting the heat consumption report.

82. If the metering unit belongs to a heat supply (heating network) organization, the consumer has the right to request copies of printouts from metering devices for the reporting period.

83. If there are reasons to doubt the reliability of the readings of metering devices, any party to the contract has the right to initiate a commission check of the functioning of the metering unit with the participation of the heat supply (heating network) organization and the consumer. The results of the commission’s work are documented in an act of checking the functioning of the metering unit.

84. If disagreements arise between the parties to the contract regarding the correctness of the readings of the metering unit, the owner of the metering unit, at the request of the other party to the contract, within 15 days from the date of application, organizes an extraordinary verification of the metering devices included in the metering unit, with the participation of a representative of the heat supply organization and the consumer.

85. If the accuracy of the meter readings is confirmed, the costs of an extraordinary verification are borne by the party to the contract that requested the extraordinary verification. If it is discovered that the meter readings are unreliable, the owner of the metering unit will bear the costs.

86. If irregularities in the operation of the metering unit are detected, the amount of thermal energy consumed is determined by the calculation method from the moment the metering device included in the metering unit fails. The time of failure of the metering device is determined from the heat meter archive data, and in their absence - from the date of submission of the last heat consumption report.

87. The owner of a metering unit is obliged to ensure:

a) unhindered access to the accounting center for the party to the contract;

b) safety of installed metering units;

c) safety of seals on measuring instruments and devices included in the metering unit.

88. If the metering unit is installed in a premises that does not belong to the owner of the metering unit on the right of ownership or other legal basis, the owner of the premises bears the responsibilities provided for in paragraph 87 of these Rules.

89. If any violations are detected in the functioning of the metering unit, the consumer is obliged to notify the service organization and the heat supply organization about this within 24 hours and draw up an act signed by representatives of the consumer and the service organization. The consumer submits this act to the heat supply organization along with a report on heat consumption for the relevant period within the time frame specified in the contract.

90. If the consumer fails to timely report violations in the functioning of the metering unit, the calculation of the consumption of thermal energy and coolant for the reporting period is carried out by calculation.

91. At least once a year, as well as after the next (extraordinary) verification or repair, the functionality of the metering unit is checked, namely:

a) the presence of seals (stamps) of the verifier and the heat supply organization;

b) validity period of the verification;

c) operability of each measurement channel;

d) compliance with the permissible measurement range for the device metering the actual values ​​of the measured parameters;

e) compliance of the characteristics of the heat meter settings with the characteristics contained in the entered database.

92. The results of checking the metering unit are documented in acts signed by representatives of the heat supply organization and the consumer.

93. The assessment of the deviation of the quality indicators of heat supply and heat consumption from the values ​​specified in the contract is carried out on the basis of the readings of metering devices included in the metering unit installed at the consumer, or portable measuring instruments. The measuring instruments used must be verified. The lack of appropriate measurements serves as a basis for rejecting consumer claims regarding the quality of thermal energy and coolant.

III. Characteristics of thermal energy and coolant to be measured for the purposes of their commercial accounting and quality control of heat supply

94. Commercial accounting of thermal energy and coolant is subject to the amount of thermal energy used, including for hot water supply, the mass (volume) of the coolant, as well as the values ​​of quality indicators of thermal energy during its supply, transmission and consumption.

95. For the purpose of commercial accounting of thermal energy, coolant and quality control of heat supply, the following is measured:

b) pressure in the supply and return pipelines;

c) coolant temperatures in the supply and return pipelines (return water temperature in accordance with the temperature chart);

d) coolant flow in the supply and return pipelines;

e) coolant flow rate in the heating and hot water supply system, including the maximum hourly flow rate;

f) the flow rate of coolant used to recharge the heating system, if there is a make-up pipeline.

96. For the purpose of commercial accounting of thermal energy, coolant and quality control of heat supply at a source of thermal energy when using steam as a coolant, the following is measured:

a) operating time of metering unit devices in normal and abnormal modes;

b) supplied thermal energy per hour, day and billing period;

c) mass (volume) of steam released and condensate returned to the heat source per hour, day and calculation period;

d) temperatures of steam, condensate and cold water per hour and per day, followed by determination of their weighted average values;

e) steam and condensate pressure per hour and per day, followed by determination of their weighted average values.

97. In open and closed heat consumption systems at the heat energy and coolant metering unit, the following is determined using a device (devices):

a) mass (volume) of coolant received through the supply pipeline and returned through the return pipeline;

b) mass (volume) of coolant received through the supply pipeline and returned through the return pipeline for each hour;

c) average hourly and average daily temperature of the coolant in the supply and return pipelines of the metering unit.

98. In open and closed heat consumption systems, the total heat load of which does not exceed 0.1 Gcal/h, at the metering station using instruments, only the operating time of the metering unit devices, the mass (volume) of the received and returned coolant, as well as the mass (volume ) coolant consumed for make-up.

99. In heat consumption systems connected according to an independent circuit, the mass (volume) of coolant consumed for make-up is additionally determined.

100. In open heat consumption systems, the following are additionally defined:

a) mass (volume) of coolant used for water collection in hot water supply systems;

b) average hourly coolant pressure in the supply and return pipelines of the metering unit.

101. Average hourly and average daily values ​​of coolant parameters are determined based on the readings of instruments recording coolant parameters.

102. In steam systems, heat consumption at the metering station is determined using instruments:

a) mass (volume) of the resulting steam;

b) mass (volume) of the returned condensate;

c) mass (volume) of steam produced per hour;

d) hourly average temperature and steam pressure;

e) average hourly temperature of the returned condensate.

103. Average hourly values ​​of coolant parameters are determined based on the readings of instruments recording these parameters.

104. In heat consumption systems connected to heating networks according to an independent scheme, the mass (volume) of condensate consumed for make-up is determined.

Heat supply quality control

105. Quality control of heat supply during the supply and consumption of heat energy is carried out at the boundaries of the balance sheet between the heat supply, heating network organization and the consumer.

106. The quality of heat supply is defined as the set of thermal energy characteristics established by regulatory legal acts of the Russian Federation and (or) the heat supply agreement, including the thermodynamic parameters of the coolant.

107. The following parameters characterizing the thermal and hydraulic regime of the heat supply system of heat supply and heating network organizations are subject to quality control of heat supply:

· pressure in the supply and return pipelines; coolant temperature in the supply pipeline in accordance with the temperature schedule specified in the heat supply contract;

b) when connecting a consumer’s heat-consuming installation through a central heating point or when directly connecting to heating networks:

· pressure in the supply and return pipelines; pressure difference at the outlet of the central heating point between the pressure in the supply and return pipelines;

· compliance with the temperature schedule at the inlet of the heating system throughout the entire heating period;

· pressure in the supply and circulation pipeline of hot water supply;

· temperature in the supply and circulation pipelines of hot water supply;

c) when connecting a consumer’s heat-consuming installation through an individual heating point:

· pressure in the supply and return pipelines; compliance with the temperature schedule at the input of the heating network throughout the entire heating period.

108. The following parameters characterizing the thermal and hydraulic conditions of the consumer are subject to quality control of heat supply:

a) when connecting the consumer’s heat-consuming installation directly to the heating network:

· return water temperature in accordance with the temperature schedule specified in the heat supply contract;

· coolant flow, including the maximum hourly flow determined by the heat supply agreement;

· consumption of make-up water determined by the heat supply agreement;

b) when connecting a consumer’s heat-consuming installation through a central heating point, an individual heating point or when directly connecting to heating networks:

· temperature of the coolant returned from the heating system in accordance with the temperature schedule;

· coolant flow in the heating system;

· consumption of make-up water according to the heat supply agreement.

109. Specific values ​​of controlled parameters are indicated in the heat supply contract.

IV. The procedure for determining the amount of supplied thermal energy and coolant for the purpose of their commercial accounting, including by calculation

110. The amount of thermal energy and coolant supplied by a source of thermal energy, for the purpose of their commercial accounting, is defined as the sum of the amounts of thermal energy and coolant in each pipeline (supply, return and make-up).

111. The amount of thermal energy and coolant received by the consumer is determined by the energy supply organization based on the readings of the consumer’s metering devices for the billing period.

112. If, in order to determine the amount of supplied (consumed) thermal energy, coolant for the purpose of commercial accounting, it is necessary to measure the temperature of cold water at the source of thermal energy, it is allowed to enter the specified temperature into the computer in the form of a constant with periodic recalculation of the amount of consumed thermal energy taking into account the actual cold water temperature. It is allowed to introduce a zero cold water temperature throughout the year.

113. The value of the actual temperature is determined:

a) for coolant - by a single heat supply organization based on data on the actual average monthly values ​​of cold water temperature at the thermal energy source provided by the owners of thermal energy sources, which are the same for all thermal energy consumers

within the boundaries of the heat supply system. The frequency of recalculation is determined in the contract;

b) for hot water - by the organization operating the central heating point, based on measurements of the actual cold water temperature in front of the hot water heaters. The frequency of recalculation is determined in the contract.

114. Determination of the amount of supplied (received) thermal energy, coolant for the purpose of commercial accounting of thermal energy, coolant (including by calculation) is carried out in accordance with the methodology for commercial accounting of thermal energy, coolant, approved by the Ministry of Construction and Housing and Communal Services of the Russian Federation (hereinafter referred to as the methodology). In accordance with the methodology, the following is carried out:

a) organization of commercial metering at the source of thermal energy, coolant and in heating networks;

b) determination of the amount of thermal energy and coolant for the purpose of their commercial accounting, including:

· the amount of thermal energy, coolant released by the source of thermal energy, coolant;

· the amount of thermal energy and mass (volume) of coolant received by the consumer;

· the amount of thermal energy and coolant consumed by the consumer during the absence of commercial metering of thermal energy and coolant using metering devices;

c) determination of the amount of thermal energy, coolant by calculation for connection through a central heating point, individual heating point, from sources of thermal energy, coolant, as well as for other connection methods;

d) determination by calculation of the amount of thermal energy and coolant for non-contractual consumption of thermal energy;

e) determination of the distribution of losses of thermal energy and coolant;

f) when operating metering devices during an incomplete billing period, adjusting the thermal energy consumption by calculation for the period of absence of readings in accordance with the methodology.

115. If there are no metering devices at the metering points or the operation of metering devices for more than 15 days of the billing period, the determination of the amount of thermal energy spent on heating and ventilation is carried out by calculation and is based on the recalculation of the base indicator for the change in outside air temperature for the entire billing period.

116. The value of the heat load specified in the heat supply contract is taken as the base indicator.

117. The base indicator is recalculated based on the actual average daily outside air temperature for the calculation period, taken according to meteorological observations of the weather station of the territorial executive body closest to the heat consumption facility, which carries out the functions of providing public services in the field of hydrometeorology.

If, during the period of cutting the temperature graph in the heating network at positive outside temperatures, there is no automatic control of the heat supply for heating, and also if the cutting of the temperature graph is carried out during a period of low outdoor temperatures, the value of the outside air temperature is taken equal to the temperature indicated at the beginning of the cut graphics. When automatically regulating the heat supply, the actual temperature value indicated at the beginning of the graph cutting is taken.

118. In the event of a malfunction of metering devices, the expiration of their verification period, including removal from work for repair or verification for up to 15 days, the average daily amount of thermal energy and coolant determined from the metering devices over time is taken as the base indicator for calculating thermal energy and coolant normal operation during the reporting period, reduced to the calculated outside air temperature.

119. If the deadlines for submitting instrument readings are violated, the amount of thermal energy and coolant determined by metering devices for the previous billing period, reduced to the calculated outside air temperature, is taken as the average daily indicator.

If the previous billing period falls on a different heating period or there is no data for the previous period, the amount of thermal energy and coolant is recalculated in accordance with paragraph 121 of these Rules.

120. The amount of thermal energy and coolant spent on hot water supply, in the presence of separate metering and temporary malfunction of devices (up to 30 days), is calculated based on the actual consumption determined by metering devices for the previous period.

121. In the absence of separate metering or inoperative condition of the devices for more than 30 days, the amount of thermal energy and coolant spent on hot water supply is assumed to be equal to the values ​​​​established in the heat supply contract (the amount of heat load on hot water supply).

122. When determining the amount of thermal energy and coolant, the amount of thermal energy supplied (received) in the event of emergency situations is taken into account. Emergency situations include:

a) operation of the heat meter at coolant flow rates below the minimum or above the maximum limit of the flow meter;

b) operation of the heat meter when the coolant temperature difference is below the minimum value established for the corresponding heat meter;

c) functional failure;

d) changing the direction of coolant flow, unless such a function is specifically included in the heat meter;

e) lack of power supply to the heat meter;

f) lack of coolant.

123. The following periods of abnormal operation of metering devices must be determined in the heat meter:

a) the duration of any malfunction (accident) of measuring instruments (including a change in the direction of coolant flow) or other devices of the metering unit that make it impossible to measure thermal energy;

b) time of power failure;

c) time of absence of water in the pipeline.

124. If the heat meter has a function for determining the time during which there is no water in the pipeline, the time of absence of water is allocated separately and the amount of thermal energy for this period is not calculated. In other cases, the time of lack of water is included in the duration of the emergency situation.

125. The amount of coolant (thermal energy) lost due to a leak is calculated in the following cases:

a) a leak, including a leak on consumer networks up to the metering station, has been identified and documented in joint documents (bilateral acts);

b) the amount of leakage recorded by the water meter when feeding independent systems exceeds the standard.

126. In the cases specified in paragraph 125 of these Rules, the leakage value is determined as the difference in the absolute values ​​of the measured values ​​without taking into account errors.

In other cases, the amount of coolant leakage determined in the heat supply contract is taken into account.

127. The mass of the coolant consumed by all consumers of thermal energy and lost in the form of leakage in the entire heat supply system from the thermal energy source is defined as the mass of the coolant consumed by the thermal energy source to recharge all pipelines of water heating networks, minus intra-station expenses for own needs during production electrical energy and in the production of thermal energy, for the production and economic needs of the objects of this source and intra-station technological losses by pipelines, units and devices within the boundaries of the source.

V. The procedure for distributing losses of thermal energy and coolant between heating networks in the absence of metering devices at the boundaries of adjacent heating networks

128. The distribution of losses of thermal energy, coolant, as well as the amount of thermal energy, coolant transferred between heating networks of heat supply organizations and heating network organizations in the absence of metering devices at the boundaries of adjacent parts of heating networks, is carried out by calculation as follows:

a) in relation to thermal energy transferred (received) at the border of the balance sheet of adjacent heating networks, the calculation is based on the balance of the amount of thermal energy supplied to the heating network and consumed by heat consuming installations of consumers (for all owner organizations and (or) other legal owners of adjacent heating networks) for all sections of pipelines at the border(s) of the balance sheet of adjacent sections of the heating network, taking into account heat energy losses associated with emergency leaks and technological losses (pressure testing, testing), losses through damaged thermal insulation in adjacent heating networks, which are documented in acts , standards

technological losses during the transfer of thermal energy and losses exceeding the approved values ​​(excessive losses);

b) in relation to the coolant transferred at the border of the balance sheet of adjacent heating networks, the calculation is based on the balance of the amount of coolant supplied to the heating network and consumed by heat-consuming installations of consumers, taking into account coolant losses associated with emergency coolant leaks, documented in acts, standards for technological losses during transfer of thermal energy approved in accordance with the established procedure, and losses exceeding the approved values ​​(exceeding norms).

129. The distribution of excess losses of thermal energy and coolant between adjacent heating networks is carried out in quantities proportional to the values ​​of the approved standards for technological losses and losses of thermal energy, taking into account emergency leaks of coolant through damaged thermal insulation.

130. In the case of transfer of thermal energy, coolant through a section of the heating network owned by the consumer, when distributing losses of thermal energy, coolant and excess losses of thermal energy, coolant, the specified heating networks are considered as adjacent heating networks.

GOVERNMENT OF THE RUSSIAN FEDERATION

RESOLUTION

On commercial metering of thermal energy and coolant


Document with changes made:
(Official Internet portal of legal information www.pravo.gov.ru, 09.12.2017, N 0001201709120007);
(Official Internet portal of legal information www.pravo.gov.ru, 02.15.2019, N 0001201902150001).
____________________________________________________________________


In accordance with the Federal Law "On Heat Supply", the Government of the Russian Federation

decides:

1. Approve the attached Rules for commercial metering of thermal energy and coolant.

2. Federal executive authorities must bring their regulatory legal acts into compliance with this resolution within 3 months.

3. The Ministry of Construction and Housing and Communal Services of the Russian Federation must approve within 2 weeks the methodology for commercial accounting of thermal energy and coolant.

Chairman of the Government
Russian Federation
D.Medvedev

Rules for commercial metering of thermal energy and coolant

APPROVED
Government resolution
Russian Federation
dated November 18, 2013 N 1034

I. General provisions

1. These Rules establish the procedure for organizing commercial metering of thermal energy and coolant, including:

a) requirements for metering devices;

b) characteristics of thermal energy, coolant, subject to measurement for the purpose of commercial accounting of thermal energy, coolant and quality control of heat supply;

c) the procedure for determining the amount of supplied thermal energy and coolant for the purpose of commercial accounting of thermal energy and coolant (including by calculation);

d) the procedure for distributing losses of thermal energy and coolant by heating networks in the absence of metering devices at the boundaries of adjacent heating networks.

2. The methodology for commercial accounting of thermal energy and coolant is determined by the methodology approved by the Ministry of Construction and Housing and Communal Services of the Russian Federation (hereinafter referred to as the methodology).

3. The terms used in these Rules mean the following:

“commissioning of a metering unit” - a procedure for checking the compliance of a thermal energy metering unit with the requirements of regulatory legal acts and design documentation, including drawing up a commissioning report for a thermal energy metering unit;

“water meter” is a measuring device designed to measure the volume (mass) of water (liquid) flowing in a pipeline through a section perpendicular to the direction of flow velocity;

“operating time of metering devices” - the time interval during which, based on the readings of metering devices, thermal energy is taken into account, as well as the mass (volume) and temperature of the coolant are measured and recorded;

“heating network output” - the output of heating networks from a source of thermal energy in a certain direction;

“computer” is a component of a heat meter that receives signals from sensors and provides calculation and accumulation of data on the amount of thermal energy and coolant parameters;

“dependent connection diagram for a heat-consuming installation” - a diagram for connecting a heat-consuming installation to a heating network, in which the coolant from the heating network flows directly into the heat-consuming installation;

“closed water heat supply system” - a complex of technologically interconnected engineering structures designed for heat supply without extracting hot water (coolant) from the heating network;

“measuring metering system” - a multi-channel measuring instrument, including channels for measuring thermal energy with measuring components - heat meters, as well as additional measuring channels for the mass (volume) of the coolant and its parameters - temperature and pressure;

“individual heating point” - a set of devices for connecting a heat-consuming installation to a heating network, converting the parameters of the coolant and distributing it by type of heat load for one building, structure or structure;

“quality of thermal energy” - a set of parameters (temperatures and pressures) of the coolant used in the processes of production, transmission and consumption of thermal energy, ensuring the suitability of the coolant for the operation of heat-consuming installations in accordance with their purpose;

“saturated steam” - water vapor that is in thermodynamic equilibrium with the water in contact with it;

“independent connection diagram for a heat-consuming installation” - a diagram for connecting a heat-consuming installation to a heating network, in which the coolant coming from the heating network passes through a heat exchanger installed at a heating point, where it heats the secondary coolant, which is subsequently used in the heat-consuming installation;

“failure of measuring instruments of a metering unit” - a state of measuring instruments in which the metering unit does not comply with the requirements of regulatory legal acts, regulatory and technical and (or) design (project) documentation (including due to the expiration of the verification period for measuring instruments included in composition of the metering unit, violation of installed seals, as well as work in emergency situations);

“open water heat supply system” - a complex of technologically interconnected engineering structures designed for heat supply and (or) hot water supply by extracting hot water (coolant) from the heating network or extracting hot water from hot water supply networks;

“superheated steam” - water vapor having a temperature higher than the saturation temperature at a certain pressure;

“make-up” is a coolant additionally supplied to the heat supply system to replenish its technological consumption and losses during the transfer of thermal energy;

“metering device” - a measuring instrument that includes technical devices that perform the functions of measuring, accumulating, storing and displaying information about the amount of thermal energy, as well as mass (volume), temperature, coolant pressure and operating time of the devices;

“coolant flow” - mass (volume) of coolant passing through the cross-section of the pipeline per unit of time;

"flow meter" - a device designed to measure coolant flow;

“calculation method” - a set of organizational procedures and mathematical actions to determine the amount of thermal energy and coolant in the absence of metering devices or their inoperability, used in the cases established by these Rules;

“temperature graph cutting” - maintaining a constant temperature of the coolant in the heating network, regardless of the outside air temperature;

“heat meter” is a device designed to measure the thermal energy emitted by the coolant or consumed together with it, which is a single structure or consisting of component elements - flow converters, flow meters, water meters, temperature (pressure) sensors and a computer;

“technical operation of a metering unit” - a set of operations for maintenance and repair of elements of a thermal energy metering unit, ensuring the reliability of measurement results;

“metering unit” - a technical system consisting of measuring instruments and devices that provide accounting for thermal energy, mass (volume) of the coolant, as well as monitoring and recording the parameters of the coolant;

“coolant leakage” - loss of water (steam) through leaks in process equipment, pipelines and heat-consuming installations;

“Measuring accounting system form” - a document drawn up in relation to the measuring system of the accounting unit and reflecting, among other things, the composition of the accounting unit and changes in its composition;

“functional failure” - a malfunction in the system of the metering unit or its elements, in which the metering of thermal energy, mass (volume) of the coolant stops or becomes unreliable;

“central heating point” is a set of devices for connecting heat-consuming installations of several buildings, structures or structures to the heating network, as well as for converting the parameters of the coolant and distributing it according to the types of heat load.

4. Commercial accounting of thermal energy and coolant is organized for the purposes of:

a) carrying out settlements between heat supply, heating network organizations and consumers of thermal energy;

b) control over the thermal and hydraulic operating conditions of heat supply systems and heat-consuming installations;

c) control over the rational use of thermal energy and coolant;

d) documenting coolant parameters - mass (volume), temperature and pressure.

5. Commercial metering of thermal energy and coolant is carried out using metering devices that are installed at the metering point located on the border of the balance sheet, if a heat supply agreement, a contract for the supply of thermal energy (power), coolant or a contract for the provision of services for the transfer of thermal energy and coolant ( hereinafter referred to as the agreement) no other accounting point has been determined.

6. Metering units put into operation before the entry into force of these Rules can be used for commercial metering of thermal energy and coolant until the expiration of the service life of the main metering devices (flow meter, heat calculator) included in the metering units.

7. After 3 years from the date of entry into force of these Rules, heat meters that do not meet the requirements of these Rules cannot be used for installation in both new and existing metering units.

8. Heat supply organizations or other persons do not have the right to require the consumer of thermal energy to install devices or additional devices at the metering station that are not provided for by these Rules.

9. The heat supply organization, heating network organization and consumer have the right to install additional devices at the metering station to control the supply and consumption of thermal energy, coolant, including for remote readings from the heat meter, without interfering with the commercial metering of heat energy, coolant and other affecting the accuracy and quality of measurements.

10. If remote reading equipment is installed at the metering station, the heat supply (heating network) organization and the consumer have the right to gain access to the specified system in the manner and on the terms determined by the contract.

11. If a single thermal energy consumer is connected to the heating network emanating from a source of thermal energy and this heating network belongs to the specified thermal energy consumer by right of ownership or other legal basis, by agreement of the parties to the contract it is allowed to keep records of the consumed thermal energy according to the readings of the device metering installed at the metering unit for the thermal energy source.

12. If one of the parties to the contract, obligated in accordance with federal laws to install a metering device, does not fulfill this obligation, the other party to the contract is obliged, in the manner established by the legislation of the Russian Federation, to install a metering device to make payments under the contract.

13. If both parties to the contract have installed a metering device, for commercial metering of thermal energy and coolant under the contract, the readings of the metering device that is installed at the balance sheet boundary are used.

If there are 2 equivalent metering units on opposite sides of the balance sheet boundary, for commercial metering of thermal energy and coolant, the readings of the metering unit are taken, providing metering with a minimum error. The error in this case consists of the amount of unmeasured heat losses from the balance sheet boundary to the metering unit and the reduced measurement error.

14. The metering devices used must comply with the requirements of the legislation of the Russian Federation on ensuring the uniformity of measurements in force at the time the metering devices are put into operation.

After the interval between verifications has expired or after the metering devices fail or are lost, if this happened before the expiration of the inter-verification interval, metering devices that do not comply with the requirements of the legislation of the Russian Federation on ensuring the uniformity of measurements are subject to verification or replacement with new metering devices.

15. Commercial metering of thermal energy and coolant is organized at all delivery and reception points.

16. Commercial accounting of thermal energy and coolant supplied to consumers of thermal energy and coolant can be organized by both heat supply organizations, heating network organizations, and consumers of thermal energy.

17. Organization of commercial accounting of thermal energy and coolant, unless otherwise provided by the provisions of these Rules, includes:

a) obtaining technical specifications for the design of a metering unit;

b) design and installation of metering devices;

c) commissioning of a metering unit;

d) operation of metering devices, including the procedure for regularly taking meter readings and using them for commercial metering of thermal energy and coolant;

e) verification, repair and replacement of metering devices.

18. Issuance of technical specifications for the installation of a metering unit (device), commissioning, sealing of metering units (devices) and participation in commissions for the acceptance of metering units (devices) is carried out without charging a fee to the thermal energy consumer.

19. Metering units are installed in a place as close as possible to the boundary of the pipelines’ balance sheet, taking into account the real possibilities at the facility.

20. At thermal energy sources, metering units are installed at each outlet of the heating network.

21. The selection of thermal energy and coolant for the own and economic needs of the thermal energy source is organized up to the metering units at the terminals. In other cases, the selection of thermal energy and coolant must be carried out through separate metering units.

The selection of coolant for replenishment of heat supply systems with the installation of a separate meter is carried out from the return pipeline after the flow sensor along the flow of the coolant. Pressure sensors can be installed both before and after the flow sensor. Temperature sensors are installed after the flow sensor along the coolant flow.

22. If sections of the heating network belong on the right of ownership or other legal basis to different persons, or if there are jumpers between heating networks that belong on the right of ownership or other legal basis to different persons, metering units must be installed at the border of the balance sheet.

23. Collection of information about the readings of metering devices, the amount of supplied (received, transported) thermal energy, coolant, the amount of thermal energy in the supplied (received, transported) hot water, the number and duration of violations that occur in the operation of metering devices, and other information provided for in the technical documentation, displayed by metering devices, as well as taking readings from metering devices (including using telemetric systems - remote reading systems) are carried out by the consumer or the heating network organization, unless otherwise provided by the agreement with the heat supply organization.

24. The consumer or heating network organization provides the organization providing water supply and (or) sanitation, before the end of the 2nd day of the month following the billing month, information on the readings of metering devices as of the 1st day of the month following the billing month, if other deadlines are not established by the legislation of the Russian Federation, as well as information about current readings of metering devices within 2 business days after receiving a request for such information from the heat supply organization. Such information is sent to the heat supply organization in any available way (postal mail, fax, telephone message, electronic message using the Internet), allowing confirmation of receipt of the specified information by the heat supply organization.

If the technical characteristics of the metering devices and metering units used allow the use of telemetric systems for transmitting meter readings and there is financial and technical support for the installation of telemetric modules and telemetric software, the presentation (taking) of meter readings is carried out remotely using such telemetric systems.

25. The consumer or heating network organization is obliged to ensure unimpeded access for representatives of the heat supply organization or, at the direction of the heat supply organization, representatives of another organization to metering units and metering devices to verify the readings of metering devices and check compliance with the operating conditions of the metering unit devices.

26. If, during the reconciliation process, a discrepancy is found in the information about the readings of the metering devices of the consumer or heating network organization regarding the volume of supplied (received) heat energy, coolant with the information provided by the consumer or heating network organization, the heat supply organization draws up a reconciliation report of the readings of the metering devices, signed by representatives consumer or heating network organization and heat supply organization.

If the representative of the consumer or heating network organization does not agree with the contents of the act of reconciling meter readings, the representative of the consumer or heating network organization marks the act as “acquainted” and affixes a signature. Objections of the consumer or heating network organization are indicated in the act or sent to the heat supply organization in writing in any way that allows confirmation of receipt of the document by the consumer or heating network organization. If a representative of a consumer or heating network organization refuses to sign the act of reconciling meter readings, such act is signed by a representative of the heat supply organization with the note “the representative of the consumer or heating network organization refused to sign.”

The act of reconciling meter readings is the basis for recalculating the volume of supplied (received) heat energy and coolant from the day of signing the act of reconciling meter readings until the day of signing the next act.

27. In order to control the volumes of supplied (received) heat energy and coolant, the heat supply organization or consumer or heating network organization has the right to use control (parallel) metering devices, provided that one of the parties to the contract notifies the other party to the contract about the use of such metering devices.

Control (parallel) metering devices are installed on the networks of the heat supply organization, heating network organization or consumer in places that allow commercial metering of heat energy, coolant supplied to the consumer, heating network organization.

If the readings of the control (parallel) metering devices and the main metering devices differ by more than the measurement error of such metering devices for a period of at least one billing month, the person who installed the control (parallel) metering device may require the other party to carry out extraordinary accounting verification of the metering device operated by this party.

28. The readings of the control (parallel) metering device are used for the purpose of commercial metering of thermal energy, coolant for the period of malfunction, verification of the main metering device, as well as in case of violation of the deadlines for submitting metering readings.

29. Installation, replacement, operation and verification of control (parallel) metering devices are carried out in accordance with the procedures provided for installation, replacement, operation and verification of main metering devices.

30. The person who installed the control (parallel) metering device is obliged to provide the other party to the contract (consumer, heating network organization, heat supply organization) with unhindered access to the control (parallel) metering devices in order to monitor the correct installation and operation of the control (parallel) metering device.

31. Commercial accounting of thermal energy and coolant by calculation is allowed in the following cases:

a) absence of metering devices at metering points;

b) malfunction of the meter;

c) violation of the deadlines established by the contract for submitting readings from metering devices that are the property of the consumer.

32. In case of non-contractual consumption of thermal energy and coolant, the amount of thermal energy and coolant used by the consumer is determined by calculation.

II. Requirements for metering devices

33. The metering unit is equipped with heat meters and metering devices, the types of which are included in the Federal Information Fund for Ensuring the Uniformity of Measurements.

34. A heat meter consists of flow and temperature (pressure) sensors, a calculator or a combination thereof. When measuring superheated steam, a steam pressure sensor is additionally installed. When connecting the consumer's heat-consuming installations to closed water heating systems according to an independent circuit, the maximum thermal load of which is less than two tenths of a gigacalorie per hour, it is allowed that the metering unit does not include a coolant flow meter in the return pipeline if there is a flow meter (water meter) on the make-up pipeline.
Decree of the Government of the Russian Federation of February 13, 2019 N 137.

Heat meters are equipped with standard industrial protocols and can be equipped with interfaces that allow remote data collection in an automatic (automated) mode. These connections should not affect the metrological characteristics of the heat meter.

If the data determined remotely and the data read directly from the heat meter do not match, the basis for determining the payment amount is the data read directly from the heat meter.

35. The design of heat meters and metering devices included in the heat meters ensures limited access to their parts in order to prevent unauthorized settings and interference, which can lead to distortion of measurement results.

36. In heat meters, correction of the internal clock of the calculator is allowed without opening the seals.

37. The heat meter calculator must have an indelible archive in which the main technical characteristics and adjustment coefficients of the device are recorded. Archive data is displayed on the device display and (or) computer. The adjustment coefficients are entered into the device passport. Any changes must be recorded in the archive.

Design of metering units

38. For a thermal energy source, the design of a metering unit measuring system is developed on the basis of a technical specification prepared by the owner of the thermal energy source and agreed with the adjacent heat supply (heating network) organization in terms of compliance with the requirements of these Rules, the terms of the contract and the conditions for connecting the thermal energy source to the heat supply system.

39. The design of a metering unit, in addition to metering points at the thermal energy source, is developed on the basis of:

a) technical conditions;

b) the requirements of these Rules and methods;

c) technical documentation for the measuring instruments used.
(Clause as amended, put into effect on February 23, 2019 by Decree of the Government of the Russian Federation dated February 13, 2019 N 137.

39_1. If the manufacturer, as part of the technical documentation for the heat meter, provides design documentation for a metering unit for thermal energy and coolant, developed on the basis of unification and typification of design, technical and technological solutions and intended for repeated use (hereinafter referred to as a standard design solution), meeting the requirements specified in subparagraphs "d" - "h", "m", "n" of paragraph 44 of these Rules, and the standard size of the flow meters corresponds to the technical specifications, then it is enough to supplement the standard design solution with documentation containing the information specified in subparagraphs "a" - "d", " i" - "l" of paragraph 44 of these Rules. For heat-consuming installations, the maximum heat load of which is less than two tenths of a gigacalorie per hour, when using a standard design solution from the heat meter manufacturer, the development of a design for a metering unit and its approval are not required.
(The paragraph was additionally included on February 23, 2019 by Decree of the Government of the Russian Federation dated February 13, 2019 N 137)

40. Specifications contain:

a) name and location of the consumer;

c) calculated parameters of the coolant at the point of delivery;

d) temperature graph of coolant supply depending on the outside air temperature;

e) requirements for ensuring the ability to connect the metering unit to the system for remote reading of the metering device using standard industrial protocols and interfaces, with the exception of requirements for installing communication means if the heat supply organization uses or plans to use such means;

f) recommendations regarding measuring instruments installed at the metering station (the heat supply organization does not have the right to impose specific types of metering devices on the consumer, but for the purpose of unification and the possibility of organizing remote collection of information from the metering station, it has the right to make recommendations).

41. The heat supply organization is obliged to issue technical specifications for the installation of a metering device within 15 working days from the date of receipt of the consumer’s request.

In the case of designing a metering unit when connecting a capital construction facility under construction or reconstruction, the requirements for metering devices (technical conditions for the installation of metering devices) are contained in the connection conditions issued in the manner established, approved by Decree of the Government of the Russian Federation dated April 16, 2012 N 307 " “On the procedure for connecting to heat supply systems and on introducing amendments to certain acts of the Government of the Russian Federation.”
Decree of the Government of the Russian Federation of September 9, 2017 N 1089)

42. If within the specified period the heat supply organization does not issue technical specifications or issues technical specifications that do not contain the information established by these Rules, the consumer has the right to independently develop a design for a metering unit and install the metering device in accordance with these Rules, of which he is obliged to notify heating supply organization.

43. If there is a ventilation and process heat load, the technical conditions are accompanied by an operating schedule and calculation of the power of heat-consuming installations.

44. The metering unit project contains:

a) a copy of the heat supply agreement with attached statements of delineation of balance sheet ownership and information on design loads for existing facilities. For newly commissioned facilities, information about design loads or connection conditions is attached;

b) plan for connecting the consumer to the heating network;

c) schematic diagram of a heating point with a metering unit;

d) plan of the heating point indicating the installation locations of sensors, placement of metering devices and cable wiring diagrams;

e) electrical and wiring diagrams for connecting metering devices;

f) a configuration database entered into the heat meter (including when switching to summer and winter operating modes);

g) a scheme for sealing measuring instruments and devices included in the metering unit, in accordance with paragraph 71 of these Rules;

h) formulas for calculating thermal energy and coolant;

i) coolant flow rate for heat-consuming installations by hour of the day in winter and summer;

j) for metering units in buildings (optional) - a table of daily and monthly heat energy consumption for heat-consuming installations;

k) forms of reporting sheets of meter readings;

l) wiring diagrams for installing flow meters, temperature sensors and pressure sensors;

m) specification of the equipment and materials used.

45. The diameter of the flow meters is selected in accordance with the calculated thermal loads so that the minimum and maximum coolant flow rates do not go beyond the normalized range of the flow meters.

46. ​​Drain devices (drainers) are provided:

a) on the supply pipeline - after the primary coolant flow converter;

b) on the return (circulation) pipeline - to the primary coolant flow converter.

48. The equipment set includes mounting inserts for replacing primary coolant flow converters and flow meters.

49. The design of a metering unit installed at a thermal energy consumer is subject to agreement with the heat supply (heating network) organization that issued the technical specifications for the installation of metering devices.

The design of a metering unit when connecting a capital construction facility under construction or reconstruction is carried out in accordance with the design documentation of the capital construction facility and (or) connection conditions. In this case, drawing up a separate project for the metering unit and its approval are not required.
(Paragraph additionally included on December 12, 2017 by Decree of the Government of the Russian Federation dated September 9, 2017 N 1089)

50. The consumer sends a copy of the metering unit design to the heat supply (heating network) organization for approval. If the metering unit project does not comply with the provisions of paragraph 44 of these Rules, the heat supply (heating network) organization is obliged, within 5 working days from the date of receipt of a copy of the metering unit project, to send a notification to the consumer about the provision of the missing documents (information).

In this case, the deadline for receipt of the metering unit project for approval is determined from the date of submission of the revised project.

51. The heat supply (heating network) organization does not have the right to refuse to approve the metering unit project if it complies with paragraph 44 of these Rules. In case of failure to provide information on approval or comments on the metering unit project within 15 working days from the date of receipt of a copy of the metering unit project, the project is considered approved.

Commissioning of a metering unit installed at a thermal energy source

52. Installed metering units (measuring systems of metering units), which have undergone trial operation, are subject to commissioning.

53. To commission the metering unit installed at the thermal energy source, the owner of the thermal energy source appoints a commission for commissioning the metering unit (hereinafter referred to as the commission) consisting of the following:

a) representative of the owner of the thermal energy source;

b) a representative of an adjacent heating network organization;

c) a representative of the organization carrying out installation and commissioning of the equipment being commissioned.

54. The representatives specified in paragraph 53 of these Rules are called by the owner of the thermal energy source no later than 10 working days before the day of expected acceptance by sending written notifications to the members of the commission.

55. To put the metering unit into operation, the owner of the thermal energy source submits to the commission:

a) schematic diagrams for connecting the terminals of the thermal energy source;

b) acts of delimitation of balance sheet ownership;

c) projects of metering units agreed upon by the heat supply (heating network) organization in the manner established by these Rules;

d) factory passports of the components of the metering unit, containing technical and metrological characteristics;

e) certificates of verification of instruments and sensors subject to verification, with valid verification marks;

f) form of the measuring system of the metering unit (if such a system is available);

g) the installed system, including instruments that record coolant parameters;

h) a statement of continuous operation of devices for 3 days.

56. When putting the metering unit into operation, the following is checked:

a) compliance of the serial numbers of measuring instruments with the numbers indicated in their passports;

b) compliance of the measurement ranges of parameters allowed by the temperature schedule and the hydraulic operating mode of heating networks with the values ​​of the specified parameters determined by the contract and the conditions of connection to the heat supply system;

c) the quality of installation of measuring instruments and communication lines, as well as compliance of installation with the requirements of technical and design documentation;

d) the presence of seals from the manufacturer or repair company and the verifier.

57. When commissioning the measuring system of a metering unit at a thermal energy source, a commissioning act for the metering unit is drawn up and the metering unit is sealed. The seals are placed by representatives of the organization that owns the heat source and the main adjacent heat supply organization.

58. The metering unit is considered suitable for commercial metering of thermal energy and coolant from the date of signing the commissioning act.

59. If a non-compliance of the metering unit with the provisions of these Rules is detected, the metering unit is not put into operation and the commissioning report provides a complete list of identified deficiencies, indicating the paragraphs of these Rules, the provisions of which were violated, and the time frame for their elimination. Such a commissioning act is drawn up and signed by all members of the commission within 3 working days.

60. Before the start of the heating period, after the next inspection or repair, the readiness of the metering unit for operation is checked, about which a report on the periodic inspection of the metering unit at the heat energy source is drawn up in the manner established by paragraphs 53-59 of these Rules.

Commissioning of a metering unit installed at the consumer, on adjacent heating networks and on jumpers

61. The installed metering unit, which has undergone trial operation, is subject to commissioning.

When connecting a capital construction facility under construction or reconstruction, information about the admission of the metering unit into operation is indicated in the act of connecting the facility to the heat supply system, drawn up in the form established by the Rules for connection to heat supply systems, approved by Decree of the Government of the Russian Federation dated April 16, 2012 N 307 " On the procedure for connecting to heat supply systems and on introducing amendments to certain acts of the Government of the Russian Federation." In this case, drawing up a separate act on putting the metering unit into operation is not required.
(Paragraph additionally included on December 12, 2017 by Decree of the Government of the Russian Federation dated September 9, 2017 N 1089)

62. Commissioning of a metering unit installed at the consumer is carried out by a commission consisting of the following:

a) a representative of the heat supply organization;

b) consumer representative;

c) a representative of the organization that carried out the installation and commissioning of the metering unit being put into operation.

63. The commission is created by the owner of the accounting center.

64. To put the metering unit into operation, the owner of the metering unit submits to the commission a draft metering unit, agreed with the heat supply organization that issued the technical specifications and passport of the metering unit or a draft passport, which includes:

a) a diagram of pipelines (starting from the balance sheet boundary) indicating the length and diameters of pipelines, shut-off valves, instrumentation, mud traps, drains and jumpers between pipelines;

b) certificates of verification of instruments and sensors subject to verification, with valid verification marks;

c) a database of setting parameters entered into the measuring unit or heat calculator;

d) a sealing scheme for measuring instruments and equipment included in the metering unit, excluding unauthorized actions that violate the reliability of commercial metering of thermal energy and coolant;

e) hourly (daily) statements of continuous operation of the metering unit for 3 days (for objects with hot water supply - 7 days).

65. Documents for putting the metering unit into operation are submitted to the heat supply organization for consideration at least 10 working days before the expected day of commissioning.

66. When accepting a metering unit for operation, the commission checks:

a) compliance of the installation of the components of the metering unit with the design documentation, technical specifications and these Rules;

b) availability of passports, certificates of verification of measuring instruments, factory seals and brands;

c) compliance of the characteristics of measuring instruments with the characteristics specified in the passport data of the metering unit;

d) compliance of the measurement ranges of parameters allowed by the temperature schedule and the hydraulic operating mode of heating networks with the values ​​of the specified parameters determined by the contract and the conditions of connection to the heat supply system.

67. If there are no comments on the metering unit, the commission signs an act of commissioning the metering unit installed at the consumer.

68. The act of commissioning a metering unit serves as the basis for maintaining commercial accounting of thermal energy, coolant using metering devices, monitoring the quality of thermal energy and heat consumption modes using the received measurement information from the date of its signing.

69. When signing the act of commissioning the metering unit, the metering unit is sealed.

70. The metering unit is sealed:

a) a representative of the heat supply organization if the metering unit belongs to the consumer;

b) a representative of the consumer who has a metering unit installed.

71. Places and devices for sealing the metering unit are prepared in advance by the installation organization. The connection points of primary transducers, connectors of electrical communication lines, protective covers on the settings and adjustment controls of devices, power supply cabinets for devices and other equipment, interference with the operation of which may lead to distortion of measurement results, are subject to sealing.

72. If members of the commission have comments on the metering unit and identify deficiencies that impede the normal functioning of the metering unit, this metering unit is considered unsuitable for commercial metering of thermal energy and coolant.

In this case, the commission draws up a report on the identified deficiencies, which provides a complete list of identified deficiencies and the deadlines for their elimination. The specified act is drawn up and signed by all members of the commission within 3 working days. Re-acceptance of the metering unit into operation is carried out after complete elimination of the identified violations.

73. Before each heating season and after the next verification or repair of metering devices, the readiness of the metering unit for operation is checked, about which a report on the periodic inspection of the metering unit at the interface of adjacent heating networks is drawn up in the manner established by paragraphs 62-72 of these Rules.

Operation of a metering unit installed at a thermal energy source

74. The owner of the thermal energy source is responsible for the technical condition of measuring instruments and devices included in the metering units installed at the thermal energy source.

75. The metering unit is considered to be out of order in the following cases:

a) lack of measurement results;

b) unauthorized interference in the operation of the metering unit;

c) violation of the installed seals on measuring instruments and devices included in the metering unit, as well as damage to electrical communication lines;

d) mechanical damage to measuring instruments and devices included in the metering unit;

e) the presence of taps into pipelines not provided for in the design of the metering unit;

f) expiration of the verification period for any of the devices (sensors);

g) work exceeding normalized limits for most of the billing period.

76. The time of failure of the metering unit installed at the source of thermal energy is recorded by an entry in the log of meter readings.

77. The representative of the owner of the heat energy source is also obliged to report to the heating network organization and the unified heat supply organization data on the readings of metering devices at the time of their failure.

78. The owner of a thermal energy source is obliged to inform the consumer about the failure of the metering devices included in the metering unit, if metering is carried out using these metering devices that are part of the metering unit installed at the thermal energy source, and transfer to the consumer the data of the instrument readings at the time their failure.

79. Representatives of the heat supply organization and consumers (if metering is carried out using devices installed at the heat energy source) are given unhindered access to the metering unit and documentation related to the metering unit.

Operation of a metering unit installed by the consumer on adjacent heating networks and on jumpers

80. Within the period established by the contract, the consumer or his authorized person submits to the heat supply organization a heat consumption report signed by the consumer. The agreement may stipulate that the heat consumption report is submitted on paper, on electronic media, or using dispatch tools (using an automated information-measuring system).

81. The consumer has the right to demand, and the heat supply organization is obliged to provide him with, a calculation of the amount of consumed thermal energy and coolant for the reporting period no later than 15 days after submitting the heat consumption report.

82. If the metering unit belongs to a heat supply (heating network) organization, the consumer has the right to request copies of printouts from metering devices for the reporting period.

83. If there are reasons to doubt the reliability of the readings of metering devices, any party to the contract has the right to initiate a commission check of the functioning of the metering unit with the participation of the heat supply (heating network) organization and the consumer. The results of the commission’s work are documented in an act of checking the functioning of the metering unit.

84. If disagreements arise between the parties to the contract regarding the correctness of the readings of the metering unit, the owner of the metering unit, at the request of the other party to the contract, within 15 days from the date of application, organizes an extraordinary verification of the metering devices included in the metering unit, with the participation of a representative of the heat supply organization and the consumer.

85. If the accuracy of the meter readings is confirmed, the costs of an extraordinary verification are borne by the party to the contract that requested the extraordinary verification. If it is discovered that the meter readings are unreliable, the owner of the metering unit will bear the costs.

86. If irregularities in the operation of the metering unit are detected, the amount of thermal energy consumed is determined by the calculation method from the moment the metering device included in the metering unit fails. The time of failure of the metering device is determined from the heat meter archive data, and in their absence - from the date of submission of the last heat consumption report.

87. The owner of a metering unit is obliged to ensure:

a) unhindered access to the accounting center for the party to the contract;

b) safety of installed metering units;

c) safety of seals on measuring instruments and devices included in the metering unit.

88. If the metering unit is installed in a premises that does not belong to the owner of the metering unit on the right of ownership or other legal basis, the owner of the premises bears the responsibilities provided for in paragraph 87 of these Rules.

89. If any violations are detected in the functioning of the metering unit, the consumer is obliged to notify the service organization and the heat supply organization about this within 24 hours and draw up an act signed by representatives of the consumer and the service organization. The consumer submits this act to the heat supply organization along with a report on heat consumption for the relevant period within the time frame specified in the contract.

90. If the consumer fails to timely report violations in the functioning of the metering unit, the calculation of the consumption of thermal energy and coolant for the reporting period is carried out by calculation.

91. At least once a year, as well as after the next (extraordinary) verification or repair, the functionality of the metering unit is checked, namely:

a) the presence of seals (stamps) of the verifier and the heat supply organization;

b) validity period of the verification;

c) operability of each measurement channel;

d) compliance with the permissible measurement range for the device metering the actual values ​​of the measured parameters;

e) compliance of the characteristics of the heat meter settings with the characteristics contained in the entered database.

92. The results of checking the metering unit are documented in acts signed by representatives of the heat supply organization and the consumer.

93. The assessment of the deviation of the quality indicators of heat supply and heat consumption from the values ​​specified in the contract is carried out on the basis of the readings of metering devices included in the metering unit installed at the consumer, or portable measuring instruments. The measuring instruments used must be verified. The lack of appropriate measurements serves as a basis for rejecting consumer claims regarding the quality of thermal energy and coolant.

III. Characteristics of thermal energy and coolant to be measured for the purposes of their commercial accounting and quality control of heat supply

94. Commercial accounting of thermal energy and coolant is subject to the amount of thermal energy used, including for hot water supply, the mass (volume) of the coolant, as well as the values ​​of quality indicators of thermal energy during its supply, transmission and consumption.

95. For the purpose of commercial accounting of thermal energy, coolant and quality control of heat supply, the following is measured:

b) pressure in the supply and return pipelines;

c) coolant temperatures in the supply and return pipelines (return water temperature in accordance with the temperature chart);

d) coolant flow in the supply and return pipelines;

e) coolant flow rate in the heating and hot water supply system, including the maximum hourly flow rate;

f) the flow rate of coolant used to recharge the heating system, if there is a make-up pipeline.

96. For the purpose of commercial accounting of thermal energy, coolant and quality control of heat supply at a source of thermal energy when using steam as a coolant, the following is measured:

a) operating time of metering unit devices in normal and abnormal modes;

b) supplied thermal energy per hour, day and billing period;

c) mass (volume) of steam released and condensate returned to the heat source per hour, day and calculation period;

d) temperatures of steam, condensate and cold water per hour and per day, followed by determination of their weighted average values;

e) steam and condensate pressure per hour and per day, followed by determination of their weighted average values.

97. In open and closed heat consumption systems at the heat energy and coolant metering unit, the following is determined using a device (devices):

a) mass (volume) of coolant received through the supply pipeline and returned through the return pipeline;

b) mass (volume) of coolant received through the supply pipeline and returned through the return pipeline for each hour;

c) average hourly and average daily temperature of the coolant in the supply and return pipelines of the metering unit.

98. In open and closed heat consumption systems, the total heat load of which does not exceed 0.1 Gcal/h, at the metering station using instruments, only the operating time of the metering unit devices, the mass (volume) of the received and returned coolant, as well as the mass (volume ) coolant consumed for make-up.

99. In heat consumption systems connected according to an independent circuit, the mass (volume) of coolant consumed for make-up is additionally determined.

100. In open heat consumption systems, the following are additionally defined:

a) mass (volume) of coolant used for water collection in hot water supply systems;

b) average hourly coolant pressure in the supply and return pipelines of the metering unit.

101. Average hourly and average daily values ​​of coolant parameters are determined based on the readings of instruments recording coolant parameters.

102. In steam systems, heat consumption at the metering station is determined using instruments:

a) mass (volume) of the resulting steam;

b) mass (volume) of the returned condensate;

c) mass (volume) of steam produced per hour;

d) hourly average temperature and steam pressure;

e) average hourly temperature of the returned condensate.

103. Average hourly values ​​of coolant parameters are determined based on the readings of instruments recording these parameters.

104. In heat consumption systems connected to heating networks according to an independent scheme, the mass (volume) of condensate consumed for make-up is determined.

Heat supply quality control

105. Quality control of heat supply during the supply and consumption of heat energy is carried out at the boundaries of the balance sheet between the heat supply, heating network organization and the consumer.

106. The quality of heat supply is defined as the set of thermal energy characteristics established by regulatory legal acts of the Russian Federation and (or) the heat supply agreement, including the thermodynamic parameters of the coolant.

107. The following parameters characterizing the thermal and hydraulic regime of the heat supply system of heat supply and heating network organizations are subject to quality control of heat supply:

pressure in the supply and return pipelines;

coolant temperature in the supply pipeline in accordance with the temperature schedule specified in the heat supply contract;

b) when connecting a consumer’s heat-consuming installation through a central heating point or when directly connecting to heating networks:

pressure difference at the outlet of the central heating point between the pressure in the supply and return pipelines;

compliance with the temperature schedule at the inlet of the heating system throughout the entire heating period;

pressure in the supply and circulation pipeline of hot water supply;

temperature in the supply and circulation pipelines of hot water supply;

c) when connecting a consumer’s heat-consuming installation through an individual heating point:

pressure in the supply and return pipelines;

compliance with the temperature schedule at the input of the heating network throughout the entire heating period.

108. The following parameters characterizing the thermal and hydraulic conditions of the consumer are subject to quality control of heat supply:

a) when connecting the consumer’s heat-consuming installation directly to the heating network:

return water temperature in accordance with the temperature schedule specified in the heat supply contract;

coolant flow rate, including the maximum hourly flow rate determined by the heat supply agreement;

make-up water consumption determined by the heat supply agreement;

b) when connecting a consumer’s heat-consuming installation through a central heating point, an individual heating point or when directly connecting to heating networks:

temperature of the coolant returned from the heating system in accordance with the temperature schedule;

coolant flow in the heating system;

make-up water consumption according to the heat supply agreement.

109. Specific values ​​of controlled parameters are indicated in the heat supply contract.

IV. The procedure for determining the amount of supplied thermal energy and coolant for the purpose of their commercial accounting, including by calculation

110. The amount of thermal energy and coolant supplied by a source of thermal energy, for the purpose of their commercial accounting, is defined as the sum of the amounts of thermal energy and coolant in each pipeline (supply, return and make-up).

111. The amount of thermal energy and coolant received by the consumer is determined by the energy supply organization based on the readings of the consumer’s metering devices for the billing period.

112. If, in order to determine the amount of supplied (consumed) thermal energy, coolant for the purpose of commercial accounting, it is necessary to measure the temperature of cold water at the source of thermal energy, it is allowed to enter the specified temperature into the computer in the form of a constant with periodic recalculation of the amount of consumed thermal energy taking into account the actual cold water temperature. It is allowed to introduce a zero cold water temperature throughout the year.

113. The value of the actual temperature is determined:

a) for coolant - by a single heat supply organization based on data on the actual average monthly values ​​of cold water temperature at the heat source provided by the owners of heat sources, which are the same for all consumers of heat within the boundaries of the heat supply system. The frequency of recalculation is determined in the contract;

b) for hot water - by the organization operating the central heating point, based on measurements of the actual cold water temperature in front of the hot water heaters. The frequency of recalculation is determined in the contract.

114. Determination of the amount of supplied (received) thermal energy, coolant for the purpose of commercial accounting of thermal energy, coolant (including by calculation) is carried out in accordance with the methodology. In accordance with the methodology, the following is carried out:
(Paragraph as amended, put into effect on February 23, 2019 by Decree of the Government of the Russian Federation dated February 13, 2019 N 137.

a) organization of commercial metering at the source of thermal energy, coolant and in heating networks;

b) determination of the amount of thermal energy and coolant for the purpose of their commercial accounting, including:

the amount of thermal energy, coolant released by the source of thermal energy, coolant;

the amount of thermal energy and mass (volume) of coolant received by the consumer;

the amount of thermal energy and coolant consumed by the consumer during the absence of commercial metering of thermal energy and coolant according to metering devices;

c) determination of the amount of thermal energy, coolant by calculation for connection through a central heating point, individual heating point, from sources of thermal energy, coolant, as well as for other connection methods;

d) determination by calculation of the amount of thermal energy and coolant for non-contractual consumption of thermal energy;

e) determination of the distribution of losses of thermal energy and coolant;

f) when operating metering devices during an incomplete billing period, adjusting the thermal energy consumption by calculation for the period of absence of readings in accordance with the methodology.

115. If there are no metering devices at the metering points or the operation of metering devices for more than 15 days of the billing period, the determination of the amount of thermal energy spent on heating and ventilation is carried out by calculation and is based on the recalculation of the base indicator for the change in outside air temperature for the entire billing period.

116. The value of the heat load specified in the heat supply contract is taken as the base indicator.

117. The base indicator is recalculated based on the actual average daily outside air temperature for the calculation period, taken according to meteorological observations of the weather station of the territorial executive body closest to the heat consumption facility, which carries out the functions of providing public services in the field of hydrometeorology.

If, during the period of cutting the temperature graph in the heating network at positive outside temperatures, there is no automatic control of the heat supply for heating, and also if the cutting of the temperature graph is carried out during a period of low outdoor temperatures, the value of the outside air temperature is taken equal to the temperature indicated at the beginning of the cut graphics. When automatically regulating the heat supply, the actual temperature value indicated at the beginning of the graph cutting is taken.

118. In the event of a malfunction of metering devices, the expiration of their verification period, including removal from work for repair or verification for up to 15 days, the average daily amount of thermal energy and coolant determined from the metering devices over time is taken as the base indicator for calculating thermal energy and coolant normal operation during the reporting period, reduced to the calculated outside air temperature.

119. If the deadlines for submitting instrument readings are violated, the amount of thermal energy and coolant determined by metering devices for the previous billing period, reduced to the calculated outside air temperature, is taken as the average daily indicator.

If the previous billing period falls on a different heating period or there is no data for the previous period, the amount of thermal energy and coolant is recalculated in accordance with paragraph 121 of these Rules.

120. The amount of thermal energy and coolant spent on hot water supply, in the presence of separate metering and temporary malfunction of devices (up to 30 days), is calculated based on the actual consumption determined by metering devices for the previous period.

121. In the absence of separate metering or inoperative condition of the devices for more than 30 days, the amount of thermal energy and coolant spent on hot water supply is assumed to be equal to the values ​​​​established in the heat supply contract (the amount of heat load on hot water supply).

122. When determining the amount of thermal energy and coolant, the amount of thermal energy supplied (received) in the event of emergency situations is taken into account. Emergency situations include:

a) operation of the heat meter at coolant flow rates below the minimum or above the maximum limit of the flow meter;

b) operation of the heat meter when the coolant temperature difference is below the minimum value established for the corresponding heat meter;

c) functional failure;

d) changing the direction of coolant flow, unless such a function is specifically included in the heat meter;

e) lack of power supply to the heat meter;

f) lack of coolant.

123. The following periods of abnormal operation of metering devices must be determined in the heat meter:

a) the duration of any malfunction (accident) of measuring instruments (including a change in the direction of coolant flow) or other devices of the metering unit that make it impossible to measure thermal energy;

b) time of power failure;

c) time of absence of water in the pipeline.

124. If the heat meter has a function for determining the time during which there is no water in the pipeline, the time of absence of water is allocated separately and the amount of thermal energy for this period is not calculated. In other cases, the time of lack of water is included in the duration of the emergency situation.

125. The amount of coolant (thermal energy) lost due to a leak is calculated in the following cases:

a) a leak, including a leak on consumer networks up to the metering station, has been identified and documented in joint documents (bilateral acts);

b) the amount of leakage recorded by the water meter when feeding independent systems exceeds the standard.

126. In the cases specified in paragraph 125 of these Rules, the leakage value is determined as the difference in the absolute values ​​of the measured values ​​without taking into account errors.

In other cases, the amount of coolant leakage determined in the heat supply contract is taken into account.

127. The mass of the coolant consumed by all consumers of thermal energy and lost in the form of leakage in the entire heat supply system from the thermal energy source is defined as the mass of the coolant consumed by the thermal energy source to recharge all pipelines of water heating networks, minus intra-station expenses for own needs during production electrical energy and in the production of thermal energy, for the production and economic needs of the objects of this source and intra-station technological losses by pipelines, units and devices within the boundaries of the source.

V. The procedure for distributing losses of thermal energy and coolant between heating networks in the absence of metering devices at the boundaries of adjacent heating networks

128. The distribution of losses of thermal energy, coolant, as well as the amount of thermal energy, coolant transferred between heating networks of heat supply organizations and heating network organizations in the absence of metering devices at the boundaries of adjacent parts of heating networks, is carried out by calculation as follows:

a) in relation to thermal energy transferred (received) at the border of the balance sheet of adjacent heating networks, the calculation is based on the balance of the amount of thermal energy supplied to the heating network and consumed by heat consuming installations of consumers (for all owner organizations and (or) other legal owners of adjacent heating networks) for all sections of pipelines at the border(s) of the balance sheet of adjacent sections of the heating network, taking into account heat energy losses associated with emergency leaks and technological losses (pressure testing, testing), losses through damaged thermal insulation in adjacent heating networks, which are documented in acts , standards for technological losses during the transfer of thermal energy and losses exceeding the approved values ​​(excessive losses);

b) in relation to the coolant transferred at the border of the balance sheet of adjacent heating networks, the calculation is based on the balance of the amount of coolant supplied to the heating network and consumed by heat-consuming installations of consumers, taking into account coolant losses associated with emergency coolant leaks, documented in acts, standards for technological losses during transfer of thermal energy approved in accordance with the established procedure, and losses exceeding the approved values ​​(exceeding norms).

129. The distribution of excess losses of thermal energy and coolant between adjacent heating networks is carried out in quantities proportional to the values ​​of the approved standards for technological losses and losses of thermal energy, taking into account emergency leaks of coolant through damaged thermal insulation.

130. In the case of transfer of thermal energy, coolant through a section of the heating network owned by the consumer, when distributing losses of thermal energy, coolant and excess losses of thermal energy, coolant, the specified heating networks are considered as adjacent heating networks.

Revision of the document taking into account
changes and additions prepared
JSC "Kodeks"